Return to this page for project updates or click on the “Subscribe” button to have updates automatically sent to your email.
April 13, 2026
City staff, the contractor, and the project engineer completed a site walk last week to review the pond improvement project. A punch list was developed, which includes remaining work items and site restoration needs. The contractor is currently preparing a project schedule, which will be coordinated by a project update once it is received.
The contractor is expected to return to the site once seasonal road restrictions are lifted, typically toward the end of April. In the meantime, City staff will be conducting additional outreach this week to residents most directly impacted, particularly where enhanced restoration efforts will be required.
March 18, 2026
Devonshire Pond
The contractor is planning to complete excavation of the channel and outlet at the Devonshire pond this week.
Redwing Pond
Excavation and outlet pipe work at the Redwing pond will be completed by Friday.
As work wraps up at these ponds, restoration will follow as the weather allows. Thank you for your patience with this project.
March 6, 2026
Crews will be working on Saturday
Devonshire Pond
Mobilization, cleaning machines and site. Begin erosion control on Devonshire Pond
Redwing Pond
Mobilization of equipment and mats to Redwing Pond and continue pumping.
February 25, 2026
Devonshire Pond
Excavating and hauling of soils will take place this week and on Saturday
Penamint Pond
Light grading may occur this week and next week, weather dependent.
February 20, 2026
The contractor is planning to work on the Devonshire pond tomorrow, Saturday, February 21st, and will continue to dewater as needed on Sunday with pumps.
February 18, 2026
Overnight water pumping will be taking place at Devonshire Pond from 2/18 through 2/19. Residents may hear a slight engine noise from the generator that is operating the pumps. The contractor will have personnel stopping by overnight to monitor the pumps and generator. Excavation work at the pond is scheduled to begin on 2/19. Thank you for your patience during this work.
February 6, 2026
The contractor is planning to work on the Devonshire pond tomorrow, Saturday, February 7th.
February 4, 2026
Anticipated schedule for Feb.
Redwing Pond
Finishing rip rap and final grading will wrap up work on this pond until restoration is completed in the spring
Devonshire Pond
Sediment removal and grading will continue for approximately the next three weeks, along with inlet/outlet repair work
Penamint Pond
Work will pick up on this pond near the end of February
January 21, 2026
anticipated schedule for Jan. 21-28
Redwing Pond
Wednesday- Finish digging basin and begin outer contour excavation and flared end rip rap.
Thursday- hauling out material and flared end work and final grading pond.
Friday – no work due to cold weather
Monday 26th - Touch ups final grade and minimal hauling. Start mobilization to next ponds.
Devonshire Pond
Wednesday and Thursday – dewatering
Mid-week mobilizing equipment to begin digging
Penamint Pond
Wednesday and Thursday – dewatering
Mid-week mobilizing equipment to begin digging
January 16, 2026
The contractor will be hauling and working on the Redwing Pond site tomorrow, Saturday,
January 17th.
January 14, 2026
Schedule for next week for Kurilla contracting is as follows,
REDWING POND
Tuesday- digging class 3 material and stockpiling and hauling class 2 material
Wednesday- Finish digging basin and begin outer contour excavation and flared end rip rap.
Thursday- hauling out material and flared end work and final grading pond.
Friday - Touch ups final grade and minimal hauling. Start mobilization to next ponds.
January 8, 2026
Pond sediment excavation and hauling at the Penamint Ct pond is scheduled to be completed early next week, weather permitting.
Tree clearing at the Devonshire Dr pond is scheduled to be finished on 1/9/26, with pond dewatering anticipated to be complete by Tuesday, 1/13/26.
December 8, 2025
The preconstruction meeting is scheduled for December 12th. The City will be receiving a construction schedule from the contractor which will be shared with the public and posted under the Project Schedule tab when it is approved.