| PROJECT NOTIFICATION DISCLAIMER |
| Due to construction variability, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they are impacted by a utility service shutdown (for example, water shutoff) or work (such as excavation or new curb) that will impede access to the property for hours or days. |
Project updates will be posted here, please check back often or click on the Subscribe button to have updates sent directly to your email.
Key Contacts:
May 8, 2026
Starting on Monday, May 11, City crews are planning to sweep/clean the streets in both neighborhoods. Houston Engineering and contractor team members will also be in both neighborhoods conducting pre-construction imagery. In the Fox Hollow neighborhood, team members will be communicating with residents regarding tree removal that is required to accommodate the project work.
Fox Hollow Neighborhood
The contractor will be starting the project work on Monday, May 18, 2026. Please note that the contractor (GMH Construction) has revised their phasing plan layout, click link. This revised plan is different than what was shared at the open house meeting on April 14, 2026.
Construction activities planned for the first week will consist of the following:
- Installation of temporary traffic control and erosion control signage/fencing/other features.
- Begin tree removal.
- Begin curb, street pavement, and driveway pavement sawcutting and removal.
Vasserman Ridge Neighborhood
The contractor will be starting the project on Monday, May 18, 2026.
Construction activities planned for the first week will consist of the following:
- Installation of temporary traffic control and erosion control signage/fencing/other features.
- Selective driveway pavement sawcutting and removal.
- Begin spot replacement and repairs of the existing sidewalk and curb including sawcutting.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Week of May 25th:
- Continuation of temporary water service installation for the Phase 1 area.
- Continuation of curb, street pavement, and driveway pavement sawcutting and removal.
- Begin watermain and storm sewer installation.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of May 25th:
- Continuation of spot replacement and repairs of the existing sidewalk and curb and selective driveway pavement sawcutting and removal.
School Busing
- Updates regarding any impacts or changes to school busing drop off and pickup will be provided.
Temporary Mailboxes
- For the Fox Hollow neighborhood, mailboxes will be removed starting on May 19. Temporary mailboxes for residents will be installed along Fox Dr.
Garbage & Recycling
- Updates regarding any impacts or changes to school busing drop off and pickup will be provided.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Irrigation & Pet Fencing: Residents are asked to mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Residents are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
April 27, 2026
The City Council conducted a public hearing and approved resolutions to accept bids, award a construction contract and adopt the final assessment roll for the 2026 City Pavement Rehabilitation Project, an annual street improvement effort that is part of the city’s long-term Pavement Management Program. The 2026 project includes approximately 2.2 miles of improvements in the Fox Hollow and Vasserman Ridge neighborhoods and follows earlier Council actions in late 2025 and early 2026.
Staff said the Vasserman Ridge area is scheduled for pavement rehabilitation along with select utility, curb, sidewalk and ADA-related upgrades. In the Fox Hollow neighborhood, most streets will undergo full reconstruction due to pavement conditions, along with watermain, drainage and related infrastructure improvements.
Additional updates near North Lotus Lake Park were developed through resident feedback and city coordination. Planned improvements include roadway adjustments, defined parking areas, trail changes and measures intended to reduce parking impacts on nearby lawns and neighborhood streets.
Staff also highlighted extensive public outreach completed throughout the planning process, including mailed notices, surveys, project webpages and multiple open houses. Resident feedback on roadway design, drainage concerns and assessments helped shape portions of the final plan.
The low bid for the project was submitted by GMH Asphalt, a contractor that has previously completed city street projects in Chanhassen. Construction is expected to begin in May, with substantial completion anticipated this fall and final restoration work continuing into 2027.
Following the public hearing, the City Council approved the resolutions unanimously.
February 6, 2026
Fox Hollow Neighborhood Pop-Up Meeting
As part of the upcoming construction project for the 26-01 Pavement Rehabilitation Project, the City has scheduled a meeting to discuss the proposed re-alignment options for the segment of the Fox Hollow Drive adjacent to North Lotus Lake Park. Proposed options will be presented as part of an open discussion with residents.
Meeting Date/Time: February 17, 2026 from 5:00pm to 6:00pm
Meeting Location: City Hall – Training Room
7700 Market Blvd., Chanhassen, MN
November 26, 2025
The City Council unanimously "ordered" the project at its November 24, 2025 meeting. There was lots of discussion and a full house of engaged residents providing comments to the Council. The Fox Hollow Drive area will be designed as a full reconstruction including watermain replacement, spot sanitary sewer repairs, storm water management and replacement of the curb and pavement. Fox Drive, however, will continue to be designed as a mill and overlay due to its newer age and condition.
The Council directed the project team to develop a design for the portion of Fox Hollow Drive by the park (the 'dogleg') that maintains the character of the existing condition, but that will also strive to improve the operations, parking availability and safety of the connection. Further outreach concerning this specific segment of the project will occur prior to the final design being considered by the City Council in the early spring.
The informational boards from the Open House can be found below:
-OVERALL MAP - VASSERMAN RIDGE NEIGHBORHOOD
-OVERALL MAP - FOX HOLLOW NEIGHBORHOOD
-INSET 1 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 2 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 3 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 1 - FOX HOLLOW NEIGHBORHOOD
-INSET 2 - FOX HOLLOW NEIGHBORHOOD
-INSET 3 - FOX HOLLOW NEIGHBORHOOD
-Assessment Board-Fox Hollow
-Assessment Board-Vasserman
-Construction Photo Collage
-Fox Hollow Dr Realignment-Option 1
-Fox Hollow Dr Realignment-Option 2
October 21, 2025
Public Open House
Wednesday, November 19, 2025
4:30 - 6:30 p.m.
Chanhassen City Hall
7700 Market Blvd,
Chanhassen, MN 55317
At this meeting you will have an opportunity to learn about the project, share your knowledge of the project area, and ask questions related to the project. This will be an informal meeting with no presentation, so feel free to join us at any time during the meeting.