2026 City Pavement Rehabilitation Project
Overview
Area 1
Approximately 1.2 miles of roadway are proposed to be improved in the Fox Hollow neighborhood. The area proposed for improvement is shown in more detail on the map to the right.
This area has not had major rehabilitations performed since the original construction (only maintenance activities such as crack seals, chip seals, and pothole patching). The project is in the final design phase and the improvements include:
- Pavement and curb reconstruction
- Stormwater management
- Sanitary sewer repairs
- Watermain replacement
Area 2
The improvements in this area include:
- Pavement resurfacing (Mill & Overlay)
- Spot curb & gutter and sidewalk replacement
- ADA improvements
- Sanitary sewer and Watermain spot repairs
Construction Phasing Map
| PROJECT NOTIFICATION DISCLAIMER |
| Due to construction variability, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they are impacted by a utility service shutdown (for example, water shutoff) or work (such as excavation or new curb) that will impede access to the property for hours or days. |
Project updates will be posted here, please check back often or click on the Subscribe button to have updates sent directly to your email.
Key Contacts:
- Lowell Moon, Project Inspector
📞 (612) 308-0118| ✉️lmoonsather@houstoneng.com - Adam Pawelk, Project Manager
📞 (952) 737-4052 | ✉️ apawelk@houstoneng.com - Ben Phillips, City Construction Manager
📞 (952) 227-1166 | ✉️ bphillips@chanhassenmn.gov
August 7, 2026
Fox Hollow Neighborhood
NOTICE: Please refrain from parking on the north side of Fox Hollow Dr. as indicated by the No Parking Signs. Limiting parking to one side of Fox Hollow Dr. is intended to create a safer environment by improving visibility and providing adequate space for the movement of vehicles and pedestrians.
NOTICE: Door hanger notices to be handed out to residents in Phases 2 and 3 informing that access to driveways will be temporarily unavailable due to the construction activities.
Construction activities planned for the Phase 1 area for the Week of August 10th:
• Begin landscaping and site restoration.
Construction activities planned for the Phase 2 area for the Week of August 10th:
• Continue street subbase reconstruction.
• Tree removal and clean up at stormwater pond inlet points (potential for this work to be pushed to the following week).
Construction activities planned for the Phase 3 area for the Week of August 10th:
• Begin removal of the ground-up pavement materials.
• Finalize temporary water connections and begin watermain installation.
• NOTICE: Door hanger notices will be handed out to residents in Phase 3 of an upcoming temporary water shut-off required to transition from the existing watermain to the temporary water service. The door hangers will include information as to when the shut-offs are scheduled to occur with the estimated duration. Included with the door hanger are instructions for residents to assist with completing the connection of the temporary water service by turning off/closing your water meter valve. The valve is located below your water meter where the water service enters your house. If you are unsure how to turn the valve off, please call Lowell Moon and assistance can be provided. This will only take a few minutes.
Vasserman Ridge Neighborhood
Remaining construction activities to occur in the coming weeks (weather permitting):
• Paint crosswalk stripping, utility repairs, and other final repairs.
• Turf restoration is scheduled for August 14th.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of August 17th:
• Finalize landscaping and site restoration.
Construction activities planned for the Phase 2 area for the Week of August 17th:
• Continue street subbase reconstruction and finalize storm sewer installation.
Construction activities planned for the Phase 3 area for the Week of August 17th:
• Continue removal of the ground-up pavement materials.
• Continue watermain installation.
July 31, 2026
Fox Hollow NeighborhoodNOTICE: Please refrain from parking on the north side of Fox Hollow Dr. as indicated by the No Parking Signs. Limiting parking to one side of Fox Hollow Dr. is intended to create a safer environment by improving visibility and providing adequate space for the movement of vehicles and pedestrians.
NOTICE: Door hanger notices to be handed out to residents in Phases 1, 2, and 3 informing that access to driveways will be temporarily unavailable due to the construction activities.
Construction activities planned for the Phase 1 area for the Week of August 3rd:
• Installation of asphalt base course.
• Begin driveway pavement repairs.
• Begin landscaping and site restoration.
Construction activities planned for the Phase 2 area for the Week of August 3rd:
• Begin street subbase reconstruction.
Construction activities planned for the Phase 3 area for the Week of August 3rd:
• Begin removal of the ground-up pavement materials.
• Continue temporary water service installation.
• NOTICE: Door hanger notices will be handed out to residents in Phase 3 of an upcoming temporary water shut-off required to transition from the existing watermain to the temporary water service. The door hangers will include information as to when the shut-offs are scheduled to occur with the estimated duration. Included with the door hanger are instructions for residents to assist with completing the connection of the temporary water service by turning off/closing your water meter valve. The valve is located below your water meter where the water service enters your house. If you are unsure how to turn the valve off, please call Lowell Moon and assistance can be provided. This will only take a few minutes.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of August 3rd (weather permitting):
• Turf restoration, paint crosswalk stripping, utility repairs, and other final repairs.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of August 10th:
• Continue landscaping and site restoration.
Construction activities planned for the Phase 2 area for the Week of August 10th:
• Continue street subbase reconstruction and finalize storm sewer installation.
Construction activities planned for the Phase 3 area for the Week of August 10th:
• Begin watermain installation.
July 24, 2026
Fox Hollow Neighborhood
NOTICE: As of July 17, 2026, the work planned for Phase 4 in Fox Hollow will now be completed as Phase 3 and the work planned for Phase 3 will be completed as Phase 4. Refer to the revised Phasing Plan.
NOTICE: Please refrain from parking on the north side of Fox Hollow Dr. as indicated by the No Parking Signs. Limiting parking to one side of Fox Hollow Dr. is intended to create a safer environment by improving visibility and providing adequate space for the movement of vehicles and pedestrians.
NOTICE: Door hanger notices to be handed out to residents in Phases 1, 2, and 3 informing that access to driveways will be temporarily unavailable due to the construction activities.
Construction activities planned for the Phase 1 area for the Week of July 27th:
• Concrete curb work. Residents will not be allowed to drive over the new curb for a period of approximately 7 days unless notified otherwise.
Construction activities planned for the Phase 2 area for the Week of July 27th:
• Finalize watermain installation and begin storm sewer installation.
Construction activities planned for the Phase 3 area for the Week of August 3rd:
• Installation of temporary traffic control and erosion control signage/fencing/other features.
• Begin curb, street pavement, and driveway pavement sawcutting and removal.
Phase 3 Residents
• Temporary Mailboxes: Mailboxes will be removed starting next week. Temporary mailboxes for Phase 3 residents will now be installed along the driveway up to the North Lotus Lake Parking lot off of Pleasantview Rd. Look for an updated notice.
• Irrigation & Pet Fencing: Residents are asked to mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
• Landscaping: Residents are asked to relocate any plantings near the roadway that they wish to save prior to work beginning.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of July 27th:
• Turf restoration, paint crosswalk stripping, utility repairs, and final curb and sidewalk repairs.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of August 3rd:
• Finalize concrete curb work.
• Asphalt paving.
Construction activities planned for the Phase 2 area for the Week of August 3rd:
• Continue storm sewer installation.
• Begin street subbase reconstruction.
Construction activities planned for the Phase 3 area for the Week of August 3rd:
• Begin removal of the ground-up pavement materials.
July 17, 2026
NOTICE: As of July 17, 2026, the work planned for Phase 4 in Fox Hollow will now be completed as Phase 3 and the work planned for Phase 3 will be completed as Phase 4. Refer to the revised Phasing Plan.
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of July 20th:
• Finalize street subbase reconstruction and storm sewer installation.
• Begin concrete curb work.
Construction activities planned for the Phase 2 area for the Week of July 20th:
• Finalize removal of the ground-up pavement materials.
• Continue watermain installation and begin storm sewer installation.
NOTICE: Door hanger notices to be handed out to residents in Phases 1 and 2 informing that access to driveways will be temporarily unavailable due to the construction activities.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of July 20th:
• Install new layer of asphalt pavement on July 22nd and 23rd.
• Finalize turf restoration, paint crosswalk stripping, and complete any final repairs.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of July 27th:
• Finalize concrete curb work.
Construction activities planned for the Phase 2 area for the Week of July 27th:
• Continue watermain and storm sewer installation.
Construction activities planned for the Phase 3 area for the Week of July 27th:
• Installation of temporary traffic control and erosion control signage/fencing/other features.
• Begin curb, street pavement, and driveway pavement sawcutting and removal.
For property owners in the Fox Hollow project area who have inquired about replacing their driveway in conjunction with the project:
We have created a list of interested property owners and provided this information to the contractor, GMH Asphalt. Typically, we receive some inquiries about full driveway replacement (paying the additional cost to replace the remaining portion of asphalt driveways). Please understand the City does not require the contractor to perform driveway replacements but they can quote them to property owners if they have an interest in the work. GMH Asphalt has indicated they will provide a quote to property owners for full asphalt driveway replacements. After GMH Asphalt provides their quote, the property owner can determine if they would like to have them complete the additional removal and replacement. Once the full driveway replacement work is completed, the City will write a reimbursement check to these property owners for the portion of the driveway replacement work which is within the current scope of the project. Houston Engineering can calculate this amount for you ahead of making your decision. This amount will be the cost the City would compensate the contractor for the replacement of the portion of your driveway the project needed to remove. Property owners who choose to hire their own contractor to replace their driveway will also be eligible to receive a similar reimbursement check. If a property owner decides to hire GMH Asphalt or hire their own contractor, please note the work must be completed in 2026 to be eligible to receive a reimbursement check. Driveways cannot be left with a gravel patch over the winter.
For property owners who have expressed interest in paying the additional cost to replace their entire concrete driveway and also for the property owners who have expressed interest in paying the additional cost to replace their asphalt driveway with concrete, the concrete subcontractor for this project has indicated they do not have the capacity to take on any additional concrete work at this time. Property owners may choose to hire their own contractor. The property owners in this situation would also be eligible to receive a reimbursement check from the City for the portion of the driveway replacement work that is within the scope of the project. Please note this work must be completed in 2026 to be eligible to receive a reimbursement check.
If you have not yet reached out to Houston Engineering about the possibility of obtaining a quote for the additional cost to replace the remaining portion of your driveway, please do so. To keep the project on schedule, we kindly ask that all coordination and decisions be made as soon as possible. If a decision has not been made on your driveway while the contractor is working on-site, they will need to repair your driveway before demobilizing from the project area. Your prompt attention is greatly appreciated. Thank you.
July 10, 2026
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of July 13th:
• Continue street subbase reconstruction.
• Continue storm sewer installation.
Construction activities planned for the Phase 2 area for the Week of July 13th:
• Continue removal of the ground-up pavement materials.
• Continue watermain installation.
• NOTICE: Door hanger notices to be handed out to residents in Phase 2 informing that access to driveways will be temporarily unavailable due to the construction activities.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of July 13th:
• Finalize sidewalk repairs.
• Turf restoration.
• Mill (grind off) top layer of asphalt pavement on July 14th and 15th.
• Final adjustments to the utility structures in the streets.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of July 20th:
• Finalize storm sewer installation.
• Begin concrete curb work.
Construction activities planned for the Phase 2 area for the Week of July 20th:
• Continuation of watermain installation.
• Begin storm sewer installation.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of July 20th:
• Install new layer of asphalt pavement on July 20th and 21st (pending weather)
• Paint crosswalk stripping.
• Complete any final repairs.
July 2, 2026
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of July 6th:
• Finalize storm sewer installation.
• Continue street subbase reconstruction.
Construction activities planned for the Phase 2 area for the Week of July 6th:
• Continue removal of the ground-up pavement materials.
• Begin watermain installation.
• NOTICE: Door hanger notices to be handed out to residents in Phase 2 informing that access to driveways will be temporarily unavailable due to the construction activities.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of July 6th:
• Finalize sidewalk repairs.
• Turf restoration.
• NOTICE: Mill (grind off) top layer of asphalt pavement has been moved to July 14th and 15th and placement of new layer of asphalt pavement has been moved to July 20th and 21st.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of July 13th:
• Continuation of street reconstruction.
Construction activities planned for the Phase 2 area for the Week of July 13th:
• Continuation of watermain installation.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of July 13th:
• Final adjustments to the utility structures in the streets.
• Mill (grind off) top layer of asphalt pavement has been moved to July 14th and 15th as noted above.
June 26, 2026
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 29th:
• Continue storm sewer installation.
• Begin street subbase reconstruction.
Construction activities planned for the Phase 2 area for the Week of June 29th:
• Begin removal of the ground-up pavement materials.
• NOTICE: Door hanger notices will be handed out to residents in Phase 2 of an upcoming temporary water shut-off required to transition from the existing watermain to the temporary water service. The door hangers will include information as to when the shut-offs are scheduled to occur with the estimated duration. Included with the door hanger are instructions for residents to assist with completing the connection of the temporary water service by turning off/closing your water meter valve. The valve is located below your water meter where the water service enters your house. If you are unsure how to turn the valve off, please call Lowell Moon and assistance can be provided. This will only take a few minutes.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 29th:
• Finalize sidewalk and utility repairs.
• Finalize irrigation repairs and begin turf restoration.
• NOTICE: Mill (grind off) top layer of asphalt pavement has been moved to July 7thand 8th and placement of new layer of asphalt pavement has been moved to July 13th and 14th.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of July 6th:
• Continuation of street subbase reconstruction.
Construction activities planned for the Phase 2 area for the Week of July 6th:
• Continuation of the removal of the ground-up pavement materials.
• Begin watermain installation.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of July 6th:
• Final adjustments to the utility structures in the streets.
• Mill (grind off) top layer of asphalt pavement has been moved to July 7th and 8th as noted above.
June 19, 2026
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 22nd:
• Begin storm sewer installation.
• NOTICE: Door hanger notices continue to be handed out to residents informing access to driveways will be temporarily unavailable.
Construction activities planned for the Phase 2 area for the Week of June 22nd:
• Begin installation of temporary water services.
• Begin curb and driveway removals.
• NOTICE: Door hanger notices to be handed out to residents informing access to driveways will be temporarily unavailable.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 22nd:
• Finalize sidewalk and curb repairs.
• Finalize irrigation and invisible fence repairs and turf restoration.
• Mill (grind off) top layer of asphalt pavement is scheduled for June 25th and 26th.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 29th:
• Continuation of storm sewer installation.
Construction activities planned for the Phase 2 area for the Week of June 29th:
• Connect homes to temporary water service system; temporary disruption to water services is anticipated.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 29th:
• Final adjustments to the utility structures in the streets.
• Placement of new layer of asphalt pavement is scheduled for July 1st and 2nd.
June 12, 2026
• Please refer to the May 22 update for information regarding Sequence of Construction that can be expected and additional project reminders.
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 15th:
• Begin removal and replacement of water service lines and shut off valves.
• NOTICE: Door hanger notices continue to be handed out to residents informing access to driveways will be temporarily unavailable.
Construction activities planned for the Phase 2 area for the Week of June 15th:
• Begin site preparation, including installing temporary mailboxes along Fox Drive and saw cut work.
• Asphalt pavement reclaim/removal work is scheduled to begin later in the week.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 15th:
• Continuation of concrete and asphalt driveway and curb repairs.
• Begin irrigation repair work on June 15th. Flags will be placed where the repairs are made. Please do not hesitate to reach out if any repairs are missed.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 22nd:
• Continuation removal and replacement of water service lines and shut off valves.
• Continuation of temporary driveway closures.
• Begin storm sewer installation.
Construction activities planned for the Phase 2 area for the Week of June 22nd:
• Begin watermain pipe removal and replacement.
• Begin temporary driveway closures.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 22nd:
• Finalize asphalt and concrete driveway and curb repairs.
• Finalize irrigation and invisible fence repairs and turf restoration.
• Mill (grind off) top layer of asphalt pavement.
June 5, 2026
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 8th:
- Watermain installation will continue.
- NOTICE: Door hanger notices continue to be handed out to residents in Phase 1 informing that access to driveways will be temporarily unavailable due to the construction activities.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 8th:
- Ridgeview Way at West 78th Street is scheduled to re-open no later than Monday, June 8th.
- Continuation of pouring concrete for driveways, sidewalks, and curb and gutter replacement areas.
- Continuation of asphalt driveway patch repairs.
- Utility repairs and adjustments, including replacing the storm structure located between 7746 and 7752 Vasserman Place.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 15th:
- Continuation of watermain pipe removal and replacement.
- Continuation of temporary driveway closures.
- Begin site preparation, including erosion control, installing temporary mailboxes, saw cut work and utility adjustments for Phase 2.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 15th:
- Finalize asphalt and concrete driveway patch repairs.
- Per the contractor’s current schedule, irrigation and invisible fence repairs and turf restoration is planned for the Week of June 22nd.
School Busing
- Updates regarding any impacts or changes to school busing drop off and pickup will be provided as needed.
Temporary Mailboxes
- For residents in the Fox Hollow neighborhood where your mailbox has been taken down, a temporary mailbox for you has been installed along Fox Dr.
Garbage & Recycling
- The Contractor will coordinate with garbage truck drivers to ensure garbage pick-up is not impacted.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Irrigation & Pet Fencing: Residents are asked to mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Residents are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Temporary Water Service: Please refer to the May 22 update for information regarding the temporary water service.
- If any residents or family members have ADA access concerns, please reach out to Lowell Moon or Adam Pawelk.
- If you have an upcoming graduation party or other events planned, feel free to reach out and we will help coordinate with the contractor to provide access for your party or event to the extent possible.
- Please refer to the May 22 update for information regarding Sequence of Construction that can be expected.
May 29, 2026
Fox Hollow Neighborhood
-
NOTICE: Door hanger notices are being handed out to residents in Phase 1 of an upcoming temporary water shut-off required to transition from the existing watermain to the temporary water service. The door hangers include information as to when the shut-offs are scheduled to occur with the estimated duration. Included with the door hanger are instructions for residents to assist with completing the connection of the temporary water service by turning off/closing your water meter valve. The valve is located below your water meter where the water service enters your house. If you are unsure how to turn the valve off, please call Lowell Moon and assistance can be provided. This will only take a few minutes.
Construction activities planned for the Phase 1 area for the Week of June 1st:
-
Begin watermain installation.
-
NOTICE: Door hanger notices are being handed out to residents in Phase 1 informing that access to driveways will be temporarily unavailable due to the construction activities. The door hangers include information as to when the interruption in access is scheduled to begin with the estimated duration as well as location for parking your vehicles.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 1st:
-
NOTICE: Starting on Monday, June 1 at 7:00am, Ridgeview Way at West. 78th Street will be temporarily closed. Please use Vasserman Trail to access West 78th Street.
-
Finalize pouring concrete for driveways, sidewalks, and curb and gutter replacement areas.
-
Utility pipe repairs.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 8th:
-
Continuation of watermain pipe removal and replacement.
-
Continuation of temporary driveway closures.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 8th:
-
Asphalt driveway patch repairs, utility repairs and adjustments, irrigation and invisible fence repairs, and turf restoration.
School Busing
-
Updates regarding any impacts or changes to school busing drop off and pickup will be provided as needed.
Temporary Mailboxes
-
For residents in the Fox Hollow neighborhood where your mailbox has been taken down, a temporary mailbox for you has been installed along Fox Dr.
Garbage & Recycling
-
The Contractor will coordinate with garbage truck drivers to ensure garbage pick-up is not impacted.
Project Reminders
-
Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
-
Irrigation & Pet Fencing: Residents are asked to mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
-
Landscaping: Residents are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
-
Temporary Water Service: Please refer to the May 22 update for information regarding the temporary water service.
-
If any residents or family members have ADA access concerns, please reach out to Lowell Moon or Adam Pawelk.
-
If you have an upcoming graduation party or other events planned, feel free to reach out and we will help coordinate with the contractor to provide access for your party or event to the extent possible.
-
Please refer to the May 22 update for information regarding Sequence of Construction that can be expected.
May 22, 2026
Fox Hollow Neighborhood
As everyone has noticed, the work has begun in the Phase 1 area including the following tasks:
- Installation of temporary traffic control and erosion control signage/fencing/other features.
- Tree removal.
- Street and driveway pavement removal including hauling the ground up pavement material to North Lotus Lake Park. This material will be re-used as part of the reconstruction of the streets. The park will be restored following construction.
- Installation of the temporary water service.
Construction activities planned for the Phase 1 area for the Week of May 25th:
- Curb and driveway pavement removal.
- Continuation of the installation of the temporary water service.
- Begin watermain installation.
Vasserman Ridge Neighborhood
As everyone has noticed, the work has begun including the following tasks:
- Sawcutting/grinding/removal of the street and driveway pavement in selected areas.
- Spot removal of sidewalk and curbs.
Construction activities planned for the Week of May 25th:
- Begin installing temporary forms followed by pouring concrete for the sidewalks and curb and gutter replacement areas.
- Utility pipe repairs.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Phase 1 area for the Week of June 1st:
- Continuation of watermain pipe removal and replacement.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of June 1st:
- Continuation of installing temporary forms followed by pouring the concrete for the sidewalks and curb and gutter replacement areas.
School Busing
- Updates regarding any impacts or changes to school busing drop off and pickup will be provided.
Temporary Mailboxes
- For residents in the Fox Hollow neighborhood where your mailbox has been taken down, a temporary mailbox for you has been installed along Fox Dr.
Garbage & Recycling
- Updates regarding any impacts or changes to garbage pickup will be provided.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Irrigation & Pet Fencing: Residents are asked to mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Residents are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Temporary Water Service: Please review the information regarding the temporary water service (link to information provided by contractor).
- If any residents or family members have ADA access concerns, please reach out to Lowell Moon or Adam Pawelk.
- If you have an upcoming graduation party or other events planned, feel free to reach out and we will help coordinate with the contractor to provide access for your party or event to the extent possible.
Sequence of construction that can be expected
- Removal limits of the driveways will be painted and saw cut.
- Pavement along each phase will be reclaimed (ground up)
- The reclaimed pavement and aggregate base will be stripped off and stockpiled at North Lotus Lake Park.
- Aggregate rock material will be placed at the end of driveways to serve as a temporary ramp.
- The next step will be for the contractor to dig down to the water service shut-off valves at each home and switch the water service over to the temporary water system.
- Once the temporary services are connected, the contractor will then begin digging up the old watermain pipe and replacing it. The amount of watermain that can be installed on a daily basis will vary.
- Once the watermain pipe has been installed and passed the necessary testing requirement, the water service pipe to each house will be connected to the new watermain pipe. Please note, if at any point you are having issues with water pressure it may likely be due to air bubbles inside the lines within your house. If so, please reach out to project staff and someone will come out to help flush your system.
- After the watermain and water service work is complete, the installation of the new storm sewer system will take place.
- Following the completion of the storm sewer installation, the existing clay road base will be dug out and replaced with sand. Then new aggregate base material will be placed on top of the sand making the street drive-able again.
- The next step will be to install temporary forms and string lines followed by pouring the concrete for the new concrete curb and gutter.
- The drain tile will then be installed along the back of the new curb. The sump pump drain boxes at each home will also be installed at this time.
- Resident driveways will then be installed.
Refer to the construction photo collage for a visual aid of the various construction activities that will be taking place.
And for anyone interested in seeing what the final product for this project will generally look like, take a drive along Frontier Trail starting at Bighorn Drive down to West 78th St. This project was completed in 2025. Additional information for this project can be found on the city web page
May 8, 2026
Starting on Monday, May 11, City crews are planning to sweep/clean the streets in both neighborhoods. Houston Engineering and contractor team members will also be in both neighborhoods conducting pre-construction imagery. In the Fox Hollow neighborhood, team members will be communicating with residents regarding tree removal that is required to accommodate the project work.
Fox Hollow Neighborhood
The contractor will be starting the project work on Monday, May 18, 2026. Please note that the contractor (GMH Construction) has revised their phasing plan layout, click link. This revised plan is different than what was shared at the open house meeting on April 14, 2026.
Construction activities planned for the first week will consist of the following:
- Installation of temporary traffic control and erosion control signage/fencing/other features.
- Begin tree removal.
- Begin curb, street pavement, and driveway pavement sawcutting and removal.
Vasserman Ridge Neighborhood
The contractor will be starting the project on Monday, May 18, 2026.
Construction activities planned for the first week will consist of the following:
- Installation of temporary traffic control and erosion control signage/fencing/other features.
- Selective driveway pavement sawcutting and removal.
- Begin spot replacement and repairs of the existing sidewalk and curb including sawcutting.
Looking Ahead
Fox Hollow Neighborhood
Construction activities planned for the Week of May 25th:
- Continuation of temporary water service installation for the Phase 1 area.
- Continuation of curb, street pavement, and driveway pavement sawcutting and removal.
- Begin watermain and storm sewer installation.
Vasserman Ridge Neighborhood
Construction activities planned for the Week of May 25th:
- Continuation of spot replacement and repairs of the existing sidewalk and curb and selective driveway pavement sawcutting and removal.
School Busing
- Updates regarding any impacts or changes to school busing drop off and pickup will be provided.
Temporary Mailboxes
- For the Fox Hollow neighborhood, mailboxes will be removed starting on May 19. Temporary mailboxes for residents will be installed along Fox Dr.
Garbage & Recycling
- Updates regarding any impacts or changes to school busing drop off and pickup will be provided.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Irrigation & Pet Fencing: Residents are asked to mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Residents are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
April 27, 2026
The City Council conducted a public hearing and approved resolutions to accept bids, award a construction contract and adopt the final assessment roll for the 2026 City Pavement Rehabilitation Project, an annual street improvement effort that is part of the city’s long-term Pavement Management Program. The 2026 project includes approximately 2.2 miles of improvements in the Fox Hollow and Vasserman Ridge neighborhoods and follows earlier Council actions in late 2025 and early 2026.
Staff said the Vasserman Ridge area is scheduled for pavement rehabilitation along with select utility, curb, sidewalk and ADA-related upgrades. In the Fox Hollow neighborhood, most streets will undergo full reconstruction due to pavement conditions, along with watermain, drainage and related infrastructure improvements.
Additional updates near North Lotus Lake Park were developed through resident feedback and city coordination. Planned improvements include roadway adjustments, defined parking areas, trail changes and measures intended to reduce parking impacts on nearby lawns and neighborhood streets.
Staff also highlighted extensive public outreach completed throughout the planning process, including mailed notices, surveys, project webpages and multiple open houses. Resident feedback on roadway design, drainage concerns and assessments helped shape portions of the final plan.
The low bid for the project was submitted by GMH Asphalt, a contractor that has previously completed city street projects in Chanhassen. Construction is expected to begin in May, with substantial completion anticipated this fall and final restoration work continuing into 2027.
Following the public hearing, the City Council approved the resolutions unanimously.
February 6, 2026
Fox Hollow Neighborhood Pop-Up Meeting
As part of the upcoming construction project for the 26-01 Pavement Rehabilitation Project, the City has scheduled a meeting to discuss the proposed re-alignment options for the segment of the Fox Hollow Drive adjacent to North Lotus Lake Park. Proposed options will be presented as part of an open discussion with residents.
Meeting Date/Time: February 17, 2026 from 5:00pm to 6:00pm
Meeting Location: City Hall – Training Room
7700 Market Blvd., Chanhassen, MN
November 26, 2025
The City Council unanimously "ordered" the project at its November 24, 2025 meeting. There was lots of discussion and a full house of engaged residents providing comments to the Council. The Fox Hollow Drive area will be designed as a full reconstruction including watermain replacement, spot sanitary sewer repairs, storm water management and replacement of the curb and pavement. Fox Drive, however, will continue to be designed as a mill and overlay due to its newer age and condition.
The Council directed the project team to develop a design for the portion of Fox Hollow Drive by the park (the 'dogleg') that maintains the character of the existing condition, but that will also strive to improve the operations, parking availability and safety of the connection. Further outreach concerning this specific segment of the project will occur prior to the final design being considered by the City Council in the early spring.
The informational boards from the Open House can be found below:
-OVERALL MAP - VASSERMAN RIDGE NEIGHBORHOOD
-OVERALL MAP - FOX HOLLOW NEIGHBORHOOD
-INSET 1 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 2 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 3 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 1 - FOX HOLLOW NEIGHBORHOOD
-INSET 2 - FOX HOLLOW NEIGHBORHOOD
-INSET 3 - FOX HOLLOW NEIGHBORHOOD
-Assessment Board-Fox Hollow
-Assessment Board-Vasserman
-Construction Photo Collage
-Fox Hollow Dr Realignment-Option 1
-Fox Hollow Dr Realignment-Option 2
October 21, 2025
Public Open House
Wednesday, November 19, 2025
4:30 - 6:30 p.m.
Chanhassen City Hall
7700 Market Blvd,
Chanhassen, MN 55317
At this meeting you will have an opportunity to learn about the project, share your knowledge of the project area, and ask questions related to the project. This will be an informal meeting with no presentation, so feel free to join us at any time during the meeting.
| Project Stage | Dates |
|---|---|
|
Advanced Public Notice |
December 2024 |
| Award Consultant Contract |
July 2025 |
| Neighborhood Project Open House |
November 19, 2025 |
| Accept Feasibility Report/Public Hearing | November 24, 2025 |
| Bid Opening | March 31, 2026 |
|
Neighborhood Open House |
April 14, 2026 |
|
Assessment Hearing/Award Contract |
April 27, 2026 |
|
Start Construction |
May 2026 |
| Substantial Completion | October 2026 |
| Final Completion | Spring 2027 |
- The City of Chanhassen's Assessment Policy is intended to provide general direction to city staff and their consultants to prepare assessment rolls to ensure fair and consistent treatment of all properties subject to an assessment. This document will also be used to educate and explain to property owners about the policy. All assessments shall follow the process outlined in Minnesota State Statutes, Chapter 429, which gives the city the legal authority to assess property.
- Pavement Management Plan - Video Series
Check out these videos to learn more about the street selection process and how it's determined which of the different types of projects is needed.
- Two Public Open Houses will be held. The first meeting will be about the Feasibility Study (November 19, 2025), and the second will be before the City Council meeting to adopt the assessments (April 14, 2026). Information from those meetings will also be linked below.
- Informational boards from Assessment Open House
-OVERALL MAP - VASSERMAN RIDGE NEIGHBORHOOD
-OVERALL MAP - FOX HOLLOW NEIGHBORHOOD
-Assessment Board-Fox Hollow
-Assessment Board-Vasserman
-Construction Photo Collage
-Pop-up Meeting-Fox Hollow Dr Realignment Update
-GMH Phasing Plan
- Informational boards from Feasibility Open House
-OVERALL MAP - VASSERMAN RIDGE NEIGHBORHOOD
-OVERALL MAP - FOX HOLLOW NEIGHBORHOOD
-INSET 1 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 2 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 3 - VASSERMAN RIDGE NEIGHBORHOOD
-INSET 1 - FOX HOLLOW NEIGHBORHOOD
-INSET 2 - FOX HOLLOW NEIGHBORHOOD
-INSET 3 - FOX HOLLOW NEIGHBORHOOD
-Assessment Board-Fox Hollow
-Assessment Board-Vasserman
-Construction Photo Collage
-Fox Hollow Dr Realignment-Option 1
-Fox Hollow Dr Realignment-Option 2
- North Lotus Lake Park Water Quality Improvement Project-Riley Purgatory Bluff Creek Watershed District
- Fox Hollow Pop-up Meeting-Realignment Update
-Realignment Update Exhibit
-Alternate Options Considered
Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.
Download Windows Media Player
Download Word Viewer
Download Excel Viewer
Download PowerPoint Viewer