2025 City Pavement Rehabilitation Project
Overview
Frontier Trail Area
Approximately 1.5 miles of roadway are proposed to be improved in the Frontier Trail neighborhood. The area proposed for improvement is shown in more detail on the map to the right.
- Frontier Trail -from Big Horn Drive to West 78th Street
- Highland Drive
- Kiowa Circle
- Conestoga Trail
- Conestoga Court
- Sierra Trail
- Sierra Court
- Del Rio Drive -from Santa Fe Trail to the NE end
- Iroquois -from Del Rio Drive to Laredo Drive
This area has not had major rehabilitations performed since the original construction (only maintenance activities such as crack seals, chip seals, and pothole patching). The project area needs to be evaluated, with anticipated improvements to include:
- Full-depth reclamation or Mill and Overlay
- Spot soil corrections or reconstruction
- Spot curb and gutter replacement
- ADA improvements
- Stormwater management spot repairs
- Sanitary sewer spot repairs
- Watermain spot repairs
................................................................................................................................................................................................
(*See Note Below)
Advance Notice postcards were also sent to the 63rd Street West neighborhood. The area proposed for improvement include:
- 63rd Street W
- Cardinal Avenue
- Koehnen Circle
- Koehnen Circle E
- Blue Jay Circle
- Audubon Circle
- Yosemite Avenue
*The 5-year Capital Improvement Plan has been modified, and your area has been removed from the 2025 project area. On March 18, 2024, the City Council voted to remove the 63rd Street West area from the 2025 City Pavement Rehabilitation Project.
- The City of Chanhassen's Assessment Policy is intended to provide general direction to city staff and their consultants to prepare assessment rolls to ensure fair and consistent treatment of all properties subject to an assessment. This document will also be used to educate and explain to property owners about the policy. All assessments shall follow the process outlined in Minnesota State Statutes, Chapter 429, which gives the city the legal authority to assess property.
- Pavement Management Plan - Video Series
Check out these videos to learn more about the street selection process and how it's determined which of the different types of projects is needed.
- Two Public Open Houses will be held (dates TBD). The first meeting will be about the Feasibility Study, and the second will be before the City Council meeting to adopt the assessments. Information from those meetings will also be linked below.
- Open House (Feasibility) -Held on January 28, 2025
- Open House (Assessment) -Scheduled for May 7, 2025
-
Here is some helpful information about construction around trees. It is more geared towards methods of protection, but if these preservation guidelines aren’t attainable, then removal has to be considered. This article touches very briefly on condition of trees, which is really important when deciding whether or not a tree is a candidate for protection.
-
A Construction Newsletter is mailed to all residents within the project area prior to construction beginning. It has a lot of information about what you can expect throughout the project as well as contact information.
| PROJECT NOTIFICATION DISCLAIMER |
| Due to construction variability, updates typically do not include specific details such as day-to-day scheduled activity. The City's inspector or contractor will notify occupants directly if they are impacted by a utility service shutdown (for example, water shutoff) or work (such as excavation or new curb) that will impede access to the property for hours or days. |
Project updates will be posted here, please check back often or click on the Subscribe button to have updates sent directly to your email
Key Contacts:
- Troy Vulcan, Senior Construction Rep
📞 (507) 848-0935 | ✉️ troy.vulcan@bolton-menk.com - Karth Whiteside, Project Engineer
📞 (612) 246-5029 | ✉️ karth.whiteside@bolton-menk.com - Ryan Johnson, Project Manager
📞 (952) 426-8335 | ✉️ ryan.johnson@bolton-menk.com
November 7, 2025
Project Access:
Paving is now complete in all of the project areas. In general, traffic should be able to travel their preferred routes at most times. There will still be construction activities that could cause delays and inconveniences, but all closures and full blocking of the roadways should be finished for the year. See attached map for access and anticipated routes out of Frontier Trail.
Week of November 10th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Street is paved.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Construction Activities: Highland to Joanna: Restoration of yards, landscaping, and miscellaneous cleanup work. Joanna to Frontier Court: Restoration of yards, landscaping, and miscellaneous cleanup work. Frontier Court to 77th Street: Street paving has been completed. Remaining bituminous driveways are anticipated to be paved on Tuesday, November 11, weather dependent. Yard restoration and landscaping items will continue. Work will continue grading and constructing the storm pond at the bottom of the hill. This work will see trucks coming in and out of that property onto Frontier Trail, so please continue to exercise caution driving in this area.
Access: Highland to 77th Street: Full access at most times. Street is paved.
Looking Ahead
All Phases
Restoration and cleanup work will continue this fall for the next few weeks. There is one more lift of pavement to be placed on most of the project streets that will occur next summer. Please reach out to the project team with any concerns or issues that remain on your property so they can make sure items are addressed. Please be aware that some of these items may be addressed next spring/summer when construction conditions are more suitable.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing drop off and pickups are moving between Frontier Trail and Great Plains Boulevard as needed. Please slow down and watch for students on all streets.
- Eastern Carver County Schools Busing: Now that paving is complete, District 112 busing will be working on getting bus routes and bus stops back to normal neighborhood locations. This change should occur in the coming weeks. Affected families will receive notifications from Eastern Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy: Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas, please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Work should be minimal for the remainder of the year.
- Lumen (CenturyLink): Work should be minimal for the remainder of the year.
- Mediacom: Work should be minimal for the remainder of the year.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
October 31, 2025
Project Access:
Please use alterantive routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of November 3rd
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Construction Activities: Highland to Joanna: Restoration of yards, landscaping, and miscellaneous cleanup work. Joanna to Frontier Court: Restoration of yards, landscaping, and miscellaneous cleanup work. Frontier Court to 77th Street: Utility work has been completed. Remaining curb to be completed early in the week followed by preparation for paving with tentative plans to pave towards the end of the week. Road work is planned for Saturday, November 1 from approximately. Work is authorized to begin at 7:30am. Please make sure vehicles are parked outside of the work zone prior to 7:30am if you will need them during the day.
Access: Highland to Joanna: Full access at most times. Street is paved. Joanna to Frontier Court: Limited access during working hours. Access to driveways overnight. Enter/Exit via Frontier Trail to the north. Please limit parking on the street during working hours as crews begin restoration along the curb. Frontier Court to 77th Street: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work.
Phase 2: Del Rio
Restoration and cleanup work.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Restoration and cleanup work.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Restoration and cleanup work.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Restoration and cleanup work.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing drop off and pickups are moving between Frontier Trail and Great Plains Boulevard as needed. Please slow down and watch for students on all streets.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas, please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Work should be minimal for the remainder of the year.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Work should be minimal for the remainder of the year.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
October 24, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of October 27th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Restoration of yards, landscaping, and miscellaneous cleanup work.
Access: Full access at most times. Streets are paved.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Construction Activities: Highland to Joanna: Restoration of yards, landscaping, and miscellaneous cleanup work. Joanna to Frontier Court: Restoration of yards, landscaping, and miscellaneous cleanup work. Frontier Court to 77th Street: Utility construction will be completed early in the week. Crews will continue building the road section. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins. Road work is planned for Saturday, October 25 from approximately 7510 Frontier Trail to 77th Street. Work is authorized to begin at 7:00am. Please make sure vehicles are parked outside of the work zone prior to 7:00am if you will need them during the day. Concrete curb and gutter is anticipated to be poured on the remainder of Frontier Trail by the end of the week, weather permitting.
Access: Highland to Joanna: Full access at most times. Street is paved. Joanna to Frontier Court: Limited access during working hours. Access to driveways overnight. Enter/Exit via Frontier Trail to the north. Frontier Court to 77th Street: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work.
Phase 2: Del Rio
Restoration and cleanup work.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Restoration and cleanup work.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Restoration and cleanup work.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Road construction should be completed the week of October 27th. Concrete curb is anticipated. Frontier Trail will be built in smaller sections so access is not limited to all residents for the entire duration of this work.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing drop off and pickups are moving between Frontier Trail and Great Plains Boulevard as needed. Please slow down and watch for students on all streets.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas, please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Work should be minimal for the remainder of the year.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Work should be minimal for the remainder of the year.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
October 17, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of October 20th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards will continue with topsoil placement and seeding/sodding installation where it is incomplete.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Crews will begin topsoil placement and seeding/sodding installation along with other miscellaneous restoration items.
Access: Full access at most times. Streets are paved.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: Crews will begin topsoil placement and seeding/sodding installation along with other miscellaneous restoration items.
Access: Full access at most times. Streets are paved.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Yard restoration and landscaping activities may begin.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Crews will begin topsoil placement and seeding/sodding installation along with other miscellaneous restoration items.
Access: Full access at most times. Streets are paved.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Construction Activities: Highland to Joanna: Crews will begin topsoil placement and seeding/sodding installation. Joanna to Frontier Court: Concrete is expected to be placed late in the week or the following week. Frontier Court to 77th Street: Utility construction, including water, sanitary, and storm pipes will continue up the hill, working towards 77th Street. Watermain and sanitary services are planned to be completed by end of week. Crews will also start building the road section towards the end of the week. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins.
Access: Highland to Joanna: Full access at most times. Street is paved. Joanna to Lift Station: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street or Frontier Trail to the north depending on where the crew is working on services on a given day. Lift Station to 77th Street: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work.
Phase 2: Del Rio
Restoration and cleanup work.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Restoration and cleanup work.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Restoration and cleanup work.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Street and utility work will continue for approximately 4-6 weeks until completion. Once storm sewer is installed, roadbed construction will begin with sand and gravel sections followed by concrete curb. Frontier Trail will be built in smaller sections so access is not limited to all residents for the entire duration of this work.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing drop off and pickups are back on Frontier Trail in front of the school. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
October 10, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of October 13th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards that will continue with topsoil placement and seeding/sodding installation where it is incomplete.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Bituminous driveway paving will continue into early the week of October 13th. Following the driveway work, crews will begin topsoil placement and seeding/sodding installation.
Access: Full access at most times. Streets are paved.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Bituminous driveway paving will continue into early the week of October 13th. Following the driveway work, crews will continue topsoil placement and seeding/sodding installation.
Access: Full access at most times. Streets are paved.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Yard restoration and landscaping activities may begin.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Bituminous driveway paving will continue into early the week of October 13th. Following the driveway work, crews will begin topsoil placement and seeding/sodding installation.
Access: Full access at most times. Streets are paved.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Construction Activities: Highland to Joanna: Crews will begin topsoil placement and seeding/sodding installation. Joanna to Frontier Court: The road section will begin to be cutout, graded, with sand and gravel installation. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins. Frontier Court to 77th Street: Utility construction, including water, sanitary, and storm pipes will continue up the hill, working towards 77th Street. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins. Rough grading for the pond is anticipated to occur.
Access: Highland to Joanna: Full access at most times. Street is paved. Joanna to Frontier Court: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street or Frontier Trail to the north depending on where the crew is working on services on a given day. Frontier Court to 77th Street: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work.
Phase 2: Del Rio
Restoration and cleanup work.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Restoration and cleanup work.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Restoration and cleanup work.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Street and utility work will continue for approximately 4-6 weeks until completion. Once storm sewer is installed, roadbed construction will begin with sand and gravel sections followed by concrete curb. Frontier Trail will be built in smaller sections so access is not limited to all residents for the entire duration of this work.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing drop off and pickups are back on Frontier Trail in front of the school. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
October 3, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of October 6th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Wear course paving is planned to start on Monday, October 6th. Restoration of yards that will continue with topsoil placement and seeding/sodding installation where it is incomplete.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Final grading of aggregate surface will occur followed by paving scheduled for Thursday, October 9th. Concrete driveways are also planned to be completed.
Access: Mostly accessible, except paving day. Access to driveways is planned to be fully open by end of week. Parking and entrance/exits via Laredo Drive and Santa Fe Trail.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: Curb replacement is planned at the storm sewer ravine crossing on Tuesday October 7th. Yard restoration and landscaping activities may begin in these locations.
Access: Mostly accessible. Street is paved from Highland Drive to Bighorn Drive except for the ravine location will be gravel surface.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Yard restoration and landscaping activities may begin. Wear course paving is planned to occur on 78th Street on Monday, October 6th.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Final grading of aggregate surface will occur followed by paving scheduled for Thursday, October 9th.
Access: Mostly accessible, except paving day. Access to driveways is planned to be fully open by end of week. Parking and entrance/exits via Laredo Drive.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Construction Activities: Highland to Joanna: Final grading of aggregate surface will occur followed by paving scheduled for Thursday, October 9th. Concrete aprons are also planned to begin. Concrete notices will be handed out to those affected. Joanna to Frontier Court: Water and sanitary service replacements will occur early in the week followed by storm sewer work. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins. Frontier Court to 77th Street: Mainline watermain placement is planned to occur midweek followed by water and sanitary service replacement. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins. Rough grading for the pond is also planned to begin later in the week.
Access: Highland to Joanna: Limited access during working hours. Access to driveways overnight. Enter/exit via Frontier Trail to the north. Joanna to Frontier Court: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street or Frontier Trail to the north depending on where the crew is working on services on a given day. Frontier Court to 77th Street: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work. It is intended that the intersection of Sierra Trail and Sierra Court will not receive the final lift this fall due to the amount of storm sewer constructed there. The final pavement in that intersection will be placed next summer.
Phase 2: Del Rio
Restoration and cleanup work.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Restoration and cleanup work.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Restoration and cleanup work.
Phase 6: Frontier Trail (Highland Drive to 77th Street)
Street and utility work will continue for approximately 5-7 weeks until completion. Once storm sewer is installed road bed construction will begin with sand and gravel sections followed by concrete curb. Frontier Trail will be built in smaller sections so access is not limited to all residents for the entire duration of this work.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing drop off and pickups are back on Frontier Trail in front of the school. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
September 26, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of September 29th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards that will continue with topsoil placement and seeding/sodding installation where it is incomplete.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Curb and gutter is scheduled for early next week on Del Rio, east of Iroquois. Access to driveways will be eliminated during the concrete placement and concrete curing. Once the curb is poured, you may park on the street near your house. Concrete notices will be handed out.
Access: Mostly accessible, except concrete days. Access to driveways overnight. Parking and entrance/exits via Laredo Drive and Santa Fe Trail.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: Storm sewer construction near the ravine is in progress and should be completed next week. This location of Frontier will be fully closed as the trench is being excavated. Yard restoration and landscaping activities may begin in these locations.
Access: Mostly accessible. Street is paved from Highland Drive to Bighorn Drive except for the ravine location will be gravel surface. During storm sewer work near the ravine, the street will be inaccessible to thru traffic. Enter/exit via Laredo Drive, Conestoga Trail, or Bighorn Drive.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Yard restoration and landscaping activities may begin.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Curb and gutter is scheduled for early next week. Access to driveways will be eliminated during the concrete placement and concrete curing. Once the curb is poured, you may park on the street near your house. Concrete notices will be handed out.
Access: No access during working hours. Access to driveways overnight. Parking and enter/exit via Laredo Drive.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Construction Activities: Highland to Joanna: Utility construction has mostly been completed in this location. Storm sewer will continue to be constructed. The crews may begin constructing the street section later next week. Joanna to Frontier Court: Forcemain installation has been completed in this location. Watermain will begin next week followed by water services. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins. Frontier Court to 77th Street: There is not currently any anticipated work to be done next week in this stretch of the neighborhood but will still see construction equipment and traffic, so continue caution while driving.
Access: Highland to Joanna: No access during working hours. Access to driveways overnight. Enter/exit via Laredo Drive. Joanna to Frontier Court: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street. Frontier Court to 77th Street: Mostly accessible at this time. Enter/exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work. Final lift of paving may occur the week of October 6. It is intended that the intersection of Sierra Trail and Sierra Court will not receive the final lift this fall due to the amount of storm sewer constructed there. The final pavement in that intersection will be placed next summer.
Phase 2: Del Rio
Paving is anticipated for the week of October 6 at this time. Restoration activities would follow that work.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction of the street in the ravine area. Paving of the street in the ravine area could occur during the week of October 6. Restoration of yards will begin in most other locations in this neighborhood.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Paving is anticipated for the week of October 6 at this time. Restoration activities would follow that work.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Street and utility work will continue for approximately 6-8 weeks until completion. Frontier Trail will be built in smaller sections so access is not limited to all residents for the entire duration of this work.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing drop off and pickups are back on Frontier Trail in front of the school. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
September 19, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of September 22nd
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards that will continue with topsoil placement and seeding/sodding installation where it is incomplete.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: The street section has been completed. The contractor anticpates constructing the curb and gutter mid-late next week on Del Rio, east of Iroquois. Access to driveways will be eliminated during the concrete placement and concrete curing. Once the curb is poured, you may park on the street near your house. Concrete notices will be given when exact days are known.
Access: Mostly accessible, except concrete days. Access to driveways overnight. Parking and entrance/exits via Laredo Drive and Santa Fe Trail.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: The contractor anticipates begin work on the storm sewer near the ravine on Tuesday with work continuing through the week. This location of Frontier will be fully closed as the trench is being excavated. Yard restoration and landscaping activities may begin in these locations.
Access: Mostly accessible. Street is paved from Highland Drive to Bighorn Drive except for the ravine location will be gravel surface. During storm sewer work near the ravine, the street will be inaccessible to thru traffic. Enter/exit via Laredo Drive, Conestoga Trail, or Bighorn Drive.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Yard restoration and landscaping activities may begin.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Next week, the contractor will continue subcutting and building up the road section. Residents will need to park outside of the construction area during working hours while the street work is being completed. It is anticipated that the street will be rock and drivable by the end of next week if weather cooperates.
Access: No access during working hours. Access to driveways overnight. Parking and enter/exit via Laredo Drive.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Construction Activities: Highland to Joanna: Utility construction will continue next week with water services, forcemain, and storm sewer.
Joanna to Frontier Court: It is possible that utility work will begin next week. This is dependent on the progress of other project locations. This work will consist of full excavation of the road, meaning the street will be inaccessible during work hours once this work begins.
Frontier Court to 77th Street: The temporary water system was successfully connected this week. There is not currently any anticipated work to be done next week in this stretch of the neighborhood but will still see construction equipment and traffic, so continue caution while driving.
Access: Highland to Joanna: No access during working hours. Access to driveways overnight. Enter/exit via Laredo Drive.
Joanna to Frontier Court: No access during working hours. Access to driveways overnight. Enter/Exit via 78th Street.
Frontier Court to 77th Street: Mostly accessible at this time. Enter/exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work. Final lift of paving will occur in the coming weeks.
Phase 2: Del Rio
Paving and restoration are the next construction activities in the weeks ahead.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction of the street in the ravine area. Restoration of yards will begin in most other locations in this neighborhood.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Paving and restoration are the next construction activities in the weeks ahead.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Utility work will commence and continue for approximately 4-6 weeks.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing has been moved to the front of the school on Great Plains Boulevard until Frontier Trail, between 77th and 78th Street, is paved. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
September 12, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of September 15th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Restoration of yards that will continue with topsoil placement and seeding/sodding installation where it is incomplete.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Crews have completed utility work along Del Rio, east of Iroquois Avenue to the Cul-de-sac. The street section will continue to be built up on the east end. The contractor anticpates working to place rock on the street on Saturday, September 13. This Saturday work may temporarily impact traffic at times as the trucks haul in and unload but residents will have access to driveways during the day on Saturday. With the excavation of the street, driveways will again be inaccessible for the week during working hours. Del Rio, west of Iroquois, has completed curb and gutter. Grading of the road will occur next week
Access: No access during working hours. Access to driveways overnight. Parking and entrance/exits via Laredo Drive and Santa Fe Trail.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: The contractor is likely to begin work on the storm sewer near the ravine next week. Yard restoration and landscaping activities may begin in these locations.
Access: Mostly accessible. Street will be paved from Highland Drive to Bighorn Drive except for the ravine location will be gravel surface. During storm sewer work near the ravine, the street will be inaccessible to thru traffic. Enter/exit via Laredo Drive, Conestoga Trail, or Bighorn Drive.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Yard restoration and landscaping activities may begin.
Access: Full access at most times. Street is paved.
Phase 5: Highland Drive
Construction Activities: Utility work has been completed. Next week, the contractor will be subcutting and building up the road section. Residents will need to park outside of the construction area during working hours while the street work is being completed.
Access: No access during working hours. Access to driveways overnight. Parking and enter/exit via Laredo Drive.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Construction Activities: Highland to Joanna: Utility construction will continue next week. Joanna to 77th Street: Removals of street, curb, and driveways will continue if not already completed. It is anticipated that the temporary water system will be connected to homes early to mid-next week. Utility work could begin late next week. It is not certain where this work will occur at this time, but likely moving south from Joanna. Updates will be provided for the next stretch of utility work once it is known.
Access: Highland to Joanna: No access during working hours. Access to driveways overnight. Enter/exit via Laredo Drive.Joanna to 77th Street: Mostly accessible in non-utility work areas. Once utility work begins, there will be no access during working hours. Access to driveways overnight. Enter/exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Patching of bituminous next to the curb. Restoration and cleanup work.
Phase 2: Del Rio
Building the street section. Curb and gutter on the east side of Del Rio may be poured following the street grading.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
The ravine area is not anticipated to be paved at that time as there will be work to complete following the storm sewer installation in that area. Restoration of yards will begin in most other locations in this neighborhood.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Street building activities will continue, followed by curb and gutter approximately the week of September 22.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Utility work will commence and continue for approximately 4-6 weeks.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing has been moved to the front of the school on Great Plains Boulevard until Frontier Trail, between 77th and 78th Street, is paved. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. They are still working on some restoration in yards. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
September 5, 2025
Project Access:
Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier Trail. ATTACHED MAP IS STREET STATUS BEGINNING TUESDAY, SEPTEMBER 9, following paving on Monday, September 8. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of September 8th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Curb and gutter will be curing for strength and access to those affected driveways will be available late next week. Restoration of yards that will continue with topsoil placement and seeding/sodding installation where it is incomplete.
Access: Full access at most times. Streets are paved.
Phase 2: Del Rio
Construction Activities: Crews will continue water service work along Del Rio, east of Iroquois Avenue to the Cul-de-sac. The water services are anticipated to be completed early next week. The street section will begin to be built up on the east end approximately the middle of next week. With the excavation of the street, driveways will again be inaccessible for the week during working hours. Del Rio, west of Iroquois, is anticipated to have aggregate surfacing that will be graded. The contractor plans to haul in and stockpile aggregate needed for the street construction on Iroquois Ave and in the cul-de-sac on Saturday, September 6. This Saturday work may temporarily impact traffic at times as the trucks haul in and unload but residents will have access to driveways during the day on Saturday.
Access: No access during working hours. Access to driveways overnight. Parking and entrance/exits via Laredo Drive and Santa Fe Trail.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: The contractor anticipates beginning work on the storm sewer near the ravine next week. Frontier Trail, south of the ravine area to Highland Drive, will be paved on Monday, September 8, weather dependent. Following paving, yard restoration activities may begin in these locations.
Access: Mostly accessible. Street will be paved from Highland Drive to Bighorn Drive except for the ravine location will be gravel surface. During storm sewer work near the ravine, the street will be inaccessible to thru traffic. Enter/exit via Laredo Drive, Conestoga Trail, or Bighorn Drive.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Concreate work has been completed. Paving is planned for Monday, September 8. Following paving, yard restoration activities may begin.
Access: Full access at most times (Beginning Tuesday, September 9). Street will be paved.
Phase 5: Highland Drive
Construction Activities: Utility work will continue for the next couple weeks. During utility work, residents will need to park outside of the construction area during working hours while the utility & street work is completed.
Access: No access during working hours. Access to driveways overnight. Parking and enter/exit via Laredo Drive.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Construction Activities: Highland to Joanna: Reclamation of the street pavement is anticipated for Wednesday, September 10. Home hookups to the temporary water system are anticipated for early next week. Removals of street, curb, and driveways will occur early next week as well. Utility construction is anticipated for mid-late next week. Joanna to 77th Street: Reclamation of the street pavement is anticipated for Wednesday, September 10. Removals of street, curb, and driveways are anticipated to begin next week as well. It is possible that the temporary water system may begin to be laid out in yards, but no hookups will be made to homes yet.
Access: Highland to Joanna: Mostly accessible early in the week. Later in the week when utility work begins: No access during working hours. Access to driveways overnight. Enter/exit via Laredo Drive. Joanna to 77th Street: Mostly accessible. Enter/exit via 78th Street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work.
Phase 2: Del Rio
Building the street section. Curb and gutter may be poured the week of September 15, on Del Rio in the whole neighborhood.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
The ravine area is not anticipated to be paved at that time as there will be work to complete following the storm sewer installation in that area. Restoration of yards will begin in most other locations in this neighborhood.
Phase 4: Frontier Trail (77th Street to 78th Street)
Restoration and cleanup work.
Phase 5: Highland Drive
Utility work will continue, followed by curb and gutter and road building activities.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Utility work will commence and continue for approximately 4-6 weeks.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing has been moved to the front of the school on Great Plains Boulevard until Frontier Trail, between 77th and 78th Street, is paved. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
August 29, 2025
Intersection Closure:
Frontier Trail at W 78th Street will be closed for the next few weeks. Please use alternative routes in and out of the neighborhoods. See attached map for access and anticipated routes out of Frontier. This map will be updated as needed and distributed primarily via email. Access routes can change daily due to changes in construction activity.
Week of September 1st
Contractor will not be working on the Labor Day holiday, Monday, September 1st
Phase 1: Conestoga Neighborhood & Kiowa Circle
Construction Activities: Driveways have been paved. There will be additional curb repairs completed next week. There is still some restoration of yards that will continue with topsoil placement and seeding/sodding installation.
Access: Full access at most times. Streets are paved. Residents to be notified if driveway closures for curb.
Phase 2: Del Rio
Construction Activities: Crews will continue watermain, sanitary service, and water service work along Del Rio, east of Iroquois Avenue to the Cul-de-sac. Utilities are very deep in this street and are taking more time than originally anticipated. Del Rio, west of Iroquois, will continue building the road section. With the excavation of the street, driveways will again be inaccessible for the week during working hours.
Access: No access during working hours. Access to driveways overnight. Parking and entrance/exits via Laredo Drive and Santa Fe Trail.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Construction Activities: Curb and gutter repairs are anticipated next week along with a couple sanitary services. Xcel Energy is scheduled to relocate the power near the ravine. This will allow the contractor to complete the storm sewer in that location next week or the following week.
Access: Mostly accessible. Street is gravel but will have some curb and pavement repair work that continues that may impede travel at times. Enter/exit via Laredo Drive, Conestoga Trail, or Bighorn Drive.
Phase 4: Frontier Trail (77th Street to 78th Street)
Construction Activities: Concreate work, including the sidewalk near the school, will be completed next week. Crews will then begin tolerancing the gravel in preparation for paving the following week.
Access: Moderate accessibility. Street is gravel but only single lane available at this time.
Phase 5: Highland Drive
Construction Activities: Utility work will continue for the next couple weeks. During utility work, residents will need to park outside of the construction area during working hours while the utility & street work is completed.
Access: No access during working hours. Access to driveways overnight. Parking and enter/exit via Laredo Drive.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Construction Activities: Layout of the temporary water system is anticipated for next week. The system will not be hooked up to homes yet, as it needs testing first.
Access: Mostly accessible. Preferred enter/exit via Laredo Drive. Access via 77th Street and 78th Street will be limited to single lane while crews work on grading the street.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and cleanup work.
Phase 2: Del Rio
Utilities are planned to continue on Del Rio, east of Iroquois, for a couple weeks before road building activities begin. It is anticipated that curb and gutter could be poured the week of September 8, on Del Rio, west of Iroquois.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Remaining storm sewer construction is anticipated for next week or the following week. There are some patches to the bituminous that need to occur the week of September 8. Paving is currently anticipated for the week of September 8 for the patches and the remaining areas from south of the ravine to Highland. The ravine area is not anticipated to be paved at that time as there will be work to complete following the storm sewer installation in that area.
Phase 4: Frontier Trail (77th Street to 78th Street)
Following concrete work, the crews will grade the road in preparation for paving. Paving is currently anticipated for the week of September 8.
Phase 5: Highland Drive
Utility work will continue, followed by curb and gutter and road building activities.
Phase 6: Frontier Trail (Highland Drive to 78th Street)Temp water system is anticipated to be connected to houses the week of September 8. That week, removals and reclamation of the street pavement is anticipated as well.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
School Busing
- Chapel Hill: Busing has been moved to the front of the school on Great Plains Boulevard until Frontier Trail, between 77th and 78th Street, is paved. Please slow down watch for students on Great Plains Boulevard.
- Eastern Carver County Schools Busing: All District 112 busing has moved bus stops out of the construction project locations. Affected families should have received emails of bus stop locations from Easter Carver County Schools Transportation. All busing questions should be directed to the ECCS Transportation Department by phone at 952-556-6160 or email at Transportation@District112.org.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Residents are asked to relocate any plantings near the roadway that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbage to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
August 22, 2025
Intersection Closure:
Frontier Trail at W 78th Street will be closed for the next few weeks. Please use alternative routes in and out of the neighborhoods.
Week of August 25th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Driveway replacements are anticipated for early next week. There is still some restoration of yards that will continue with topsoil placement and seeding/sodding installation.
Phase 2: Del Rio
Crews will continue watermain, sanitary service, and water service work along Del Rio, east of Iroquois Avenue to the Cul-de-sac. Del Rio, west of Iroquois, will be building the road section. With the excavation of the street, driveways will again be inaccessible for the week during working hours.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Water services have been completed. The temporary water system is anticipated to be removed and homes placed back onto the watermain next week. Bituminous driveways are anticipated to be poured on Tuesday, weather dependent. There may be limited work in this phase next week as the contractor waits for electric relocations to occur prior to storm sewer construction commencing near the ravine.
Phase 4: Frontier Trail (77th Street to 78th Street)
Crews will continue building the street section from Chan View to 77th Street. Curb and gutter is anticipated to be poured from 77th Street to 78th Street on Tuesday, weather permitting.
Phase 5: Highland Drive
Driveway and curb removals are anticipated to begin next week. The temporary water system is anticipated to be setup next week in preparation for utility work. Utility work is anticipated to begin on Tuesday. Once utility work begins, residents will need to park outside of the construction area during working hours while the utility & street work is completed.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Restoration and clean up work.
Phase 2: Del Rio
Utilities are planned to continue for a few weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Remaining storm sewer construction is anticipated for the week following Labor Day. Finish grading the gravel and make curb and gutter spot repairs. Paving is currently anticipated for early-mid September.
Phase 4: Frontier Trail (77th Street to 78th Street)
Following concrete work, the crews will grade the road in preparation for paving. Paving is currently anticipated for mid-September.
Phase 5: Highland Drive
Utility work will continue, followed by curb and gutter and road building activities.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Work in this area is planned to begin in early September.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas relocations have been completed project wide. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
August 15, 2025
Intersection Closure:
Frontier Trail at W 78th Street will be closed for the next few weeks. Please use alterantive routes in and out of the neighborhoods.
Week of August 18th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Following paving, restoration of yards will continue with topsoil placement and seeding/sodding installation.
Phase 2: Del Rio
Crews will continue watermain, sanitary service, and water service work along Del Rio, east of Iroquois Avenue to the Cul-de-sac. Del Rio, west of Iroquois will begin building the road section. With the excavation of the street, driveways will again be inaccessible for the week during working hours.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
On the north end of Frontier, paving should be completed Friday, August 15th unless rain causes a delay to next week. Paving limits are anticipated to stop just south of Kiowa Circle. A few water service reconnections remain between Kiowa Circle and Highland Drive, these anticipated to be finished next week. Street crews will finish grading the road section south of Kiowa Circle on Frontier Trail and repair spot curb and gutter.
Phase 4: Frontier Trail (77th Street to 78th Street)
Crews will continue building the street section from Chan View to 77th Street. Curb and gutter will be poured between 78th Street and Chan View. Notices will be delivered about driveway access.
Phase 5: Highland Drive
Driveway and curb removals are anticipated to begin next week. The temporary water system is anticipated to be setup next week in preparation for utility work. Utility work is anticipated to begin later in the week or early the following week. Once utility work begins, residents will need to park outside of the construction area during working hours while the utility & street work is completed. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
The contractor will complete the yard restoration. There will be one more lift of pavement coming later in the year.
Phase 2: Del Rio
Utilities are planned to continue for a few weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Finish grading the gravel and make curb and gutter spot repairs. Paving is currently anticipated for early September.
Phase 4: Frontier Trail (77th Street to 78th Street)
Curb and gutter and sidewalk will be the next items constructed. Paving is currently anticipated for mid-September.
Phase 5: Highland Drive
Utility work is anticipated to begin in mid-August followed by road building activities begin.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Work in this area is planned to begin in late August with utility work expected to last about 4 weeks followed by road building.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed project wide. Service connections to the new mains are on-going project wide. CenterPoint Energy will coordinate with residents directly on service impacts. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
August 8, 2025
Intersection Closure:
Frontier Trail at W 78th Street will be closed for the next few weeks. Please use alternative routes in and out of the neighborhoods.
Week of August 11th
Phase 1: Conestoga Neighborhood & Kiowa Circle
The pavement in the Conestoga neighborhood will be reclaimed on Monday, August 11th. No parking is allowed in the street that day, but access to driveways will be available most of the day. Street crews will finish grading the road section on Conestoga Trail, Conestoga Circle, Sierra Trail, Sierra Court, Kiowa Circle, and the north portion of Frontier Trail. The first lift of paving is currently anticipated for Phase 1 on Friday, August 15th. Paving will be weather dependent and may change. Restoration of yards will continue with topsoil placement and seeding/sodding installation.
Phase 2: Del Rio
It is anticipated that storm sewer will be constructed on Iroquois Avenue and the intersection of Del Rio on Monday, August 11th. This will block access at the intersection. Crews will continue watermain, sanitary service, and water service work along Del Rio, east of Iroquois Avenue to the Cul-de-sac. Due to Del Rio being a dead-end street, residents will need to park outside of the construction area multiple days in a row during working hours while the utility & street work is completed. It is the intent of the project team to have driveway access restored at the end of each day. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Water service reconnections will continue throughout the week. Residents will remain on temporary water for a few more weeks while bacteria and pressure testing occur on the newly lined watermain and services. Most of the remaining pavement is scheduled to be reclaimed on Monday, August 11th. No parking is allowed in the street that day, but access to driveways will be available most of the day. Street crews will finish grading the road section on Frontier Trail and repair spot curb and gutter.
Phase 4: Frontier Trail (77th Street to 78th Street)
Storm sewer installation from 77th Street to Chan View will be completed. Crews will continue building the street section. Access to driveways along Frontier will be limited during working hours. It is the intent of the project team to have driveway access restored at the end of each day. It is possible that curb and gutter will be poured late in the week between 78th Street and Chan View. If concrete occurs, notices will be delivered about driveway access.
Phase 5: Highland Drive
Work will begin on Highland Drive on Monday, August 11th with reclaiming of the pavement and temporary water systems being installed. Utility work is anticipated to begin later in the week or early the following week. Once utility work begins, residents will need to park outside of the construction area during working hours while the utility & street work is completed. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Following the base course of paving, the contractor will complete the yard restoration. There will be one more lift of pavement coming later in the year.
Phase 2: Del Rio
Utilities are planned to continue for a few weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
The remainder of the street will be reclaimed to gravel. Then the next steps are to grade the gravel and make curb and gutter spot repairs.
Phase 4: Frontier Trail (77th Street to 78th Street)
Utility work will wrap up soon and continue building the street section.
Phase 5: Highland Drive
Utility work is anticipated to begin in mid-August followed by road building activities begin.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Work in this area is planned to begin in late August with utility work expected to last about 4 weeks followed by road building.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed project wide. Service connections to the new mains are on-going project wide. CenterPoint Energy will coordinate with residents directly on service impacts. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
August 1, 2025
Intersection Closure:
Frontier Trail at W 78th Street will be closed for the next few weeks. Please use alternative routes in and out of the neighborhoods.
Week of August 4th
Phase 1: Conestoga Neighborhood & Kiowa Circle
It is anticipated that the storm sewer at Sierra Trail and Sierra Court will be completed. Street crews will finish building the road section in Kiowa Circle. Early next week the new curb will be constructed on Kiowa Circle. Once new concrete is placed, vehicles cannot drive over it for 7 days while it cures. Access to driveways and the street may be impacted during working hours.
Phase 2: Del Rio
Crews will continue watermain, sanitary service, and water service work along Del Rio between Santa Fe Trail and Iroquois Avenue before moving to the section from Iroquois Avenue to the Cul-de-sac. This transition might occur mid-week. Due to Del Rio being a dead-end street, residents may have to park outside of the construction area multiple days in a row during working hours while the utility & street work is completed. It is the intent of the project team to have driveway access restored at the end of each day. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Watermain and forcemain lining is complete. Water service reconnections will continue throughout the week. Residents will remain on temporary water for a few more weeks while bacteria and pressure testing occur on the newly lined watermain and services.
Phase 4: Frontier Trail (77th Street to 78th Street)
Crews will continue with watermain and storm sewer work in the area. Access to driveways along Frontier will be limited during working hours as the utility trenches will make the roadway impassable. It is the intent of the project team to have driveway access restored at the end of each day. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Once storm sewer and concrete placement are completed, that will be followed by final reclamation of the roadway surface before tolerancing the gravel in preparation for paving. Paving is currently anticipated to occur in mid-August.
Phase 2: Del Rio
Utilities are planned to last approximately 4 weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Replacement of existing water services will continue. Following water services the remainder of the street will be reclaimed to gravel. Then the next steps are to grade the gravel and make curb and gutter spot repairs.
Phase 4: Frontier Trail (77th Street to 78th Street)
Utility work will continue in this section with replacement of the watermain, water services, storm sewer, and sanitary sewer services. Utility work is expected to last approximately 3 weeks followed by road building activities.
Phase 5: Highland Drive
Work in this area is planned to begin in mid-August with temporary water systems being installed. Utility work is anticipated to begin in late-August and last 3 weeks before road building activities begin.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Work in this area is planned to begin in late August with utility work expected to last about 4 weeks followed by road building.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed project wide. Service connections to the new mains are on-going project wide. CenterPoint Energy will coordinate with residents directly on service impacts. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Some limited underground relocations will continue at times throughout the project area to accommodate utility construction needs.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and will be occurring as needed with street and utility construction needs.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
July 25, 2025
Intersection Closure:
Frontier Trail at W 78th Street will be closed for the next few weeks. Please use alternative routes in and out of the neighborhoods.
Week of July 28th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Crews will finish up any remaining concrete curb & gutter and driveway removals followed by placement of new concrete curb & gutter. Once new concrete is placed, vehicles cannot drive over it for 7 days while it cures. A separate notice will be handed out to those with affected driveway access. It is anticipated that the storm sewer at Sierra Trail and Sierra Court will be completed. Street building crews will continue building the road section in Kiowa Circle. Access to driveways and the street may be impacted during working hours.
Phase 2: Del Rio
Crews will continue watermain, sanitary service, and water service work along Del Rio between Santa Fe Trail and Iroquois Avenue before moving to the section from Iroquois Avenue to the Cul-de-sac. Due to Del Rio being a dead-end street, residents may have to park outside of the construction area multiple days in a row during working hours while the utility & street work is completed. It is the intent of the project team to have driveway access restored at the end of each day. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Watermain lining will be wrapping up on the mainline water early in the week. Service reconnections could potentially occur mid-week. Residents will remain on temporary water for a few more weeks while bacteria and pressure testing occur on the newly lined watermain and services. The lining crew also plans to begin lining work on the existing sanitary forcemain and a temporary bypass system has been set up.
Phase 4: Frontier Trail (77th Street to 78th Street)
Crews will continue with utility work in the area.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Once storm sewer and concrete placement are completed, that will be followed by final reclamation of the roadway surface before tolerancing the gravel in preparation for pavement in the coming weeks.
Phase 2: Del Rio
Utilities are planned to last approximately 4 weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Lining of the existing watermain and replacement of existing water services are anticipated to last approximately 7 weeks. Forcemain lining is planned to begin soon.
Phase 4: Frontier Trail (77th Street to 78th Street)
Utility work will continue in this section with replacement of the watermain, water services, storm sewer, and sanitary sewer services. Utility work is expected to last approximately 3 weeks followed by road building activities.
Phase 5: Highland Drive
Work in this area is planned to occur in mid-August with temporary water systems being installed. Utility work is anticipated to begin in late-August and last 3 weeks before road building activities begin.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Work in this area is planned to begin in mid to late August with utility work expected to last about 4 weeks followed by road building.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed project wide. Service connections to the new mains are on-going project wide. CenterPoint Energy will coordinate with residents directly on service impacts. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Pole and streetlight relocations are planned. Xcel plans to start pole relocations next week along with some underground line relocations.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and is scheduled to begin after the holiday weekend and last approximately 2-3 weeks.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
July 18, 2025
Intersection Closure:
The intersections of Frontier Trail & W 77th Street and Frontier Trail & Chan View will be closed to all traffic on Monday, July 21st for utility work. Access to Frontier Trail from W 78th Street will also be closed for the next few weeks. Please use alternative routes in and out of the neighborhoods.
Week of July 14th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Utility crews plan to finish up storm sewer in Conestoga neighborhood. They then plan to begin concrete curb & gutter and driveway removals followed by placement of new concrete curb & gutter. Once new concrete is placed, vehicles cannot drive over it for 7 days while it cures. A separate notice will be handed out to those with affected driveway access. Street building crews will start excavating and building the road section in Kiowa Circle. Access to driveways and the street may be impacted during working hours.
Phase 2: Del Rio
Crews will continue watermain and sanitary sewer work along Del Rio between Santa Fe Trail and Iroquois Avenue. Due to Del Rio being a dead end street, residents may have to park outside of the construction area multiple days in a row during working hours while the utility & street work is completed. It is the intent of the project team to have driveway access restored at the end of each day. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Watermain lining will continue on the mainline water.
Phase 4: Frontier Trail (77th Street to 78th Street)
Crews plan to begin stripping gravel reclaim off of this section starting Monday morning followed by a watermain shutdown to make necessary connections at the intersections in order to complete work on the mainline watermain. There will be temporary intersection closures throughout the week to complete the work.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Concrete placement will be completed follow by final reclamation of the roadway surface before tolerancing the gravel in preparation for pavement in the coming weeks.
Phase 2: Del Rio
Utilities are planned to last approximately 5 weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Lining of the existing watermain and replacement of existing water services are anticipated to last approximately 7 weeks.
Phase 4: Frontier Trail (77th Street to 78th Street)
Utility work will continue in this section with replacement of the watermain, water services, storm sewer, and sanitary sewer services. Utility work is expected to last approximately 3 weeks followed by road building activities.
Phase 5: Highland Drive
Work in this area is planned to occur in early August with temporary water systems being installed. Utility work is anticipated to begin in mid-August and last 3 weeks before road building activities begin.
Phase 6: Frontier Trail (Highland Drive to 78th Street)
Work in this area is planned to begin in mid to late August with utility work expected to last about 4 weeks followed by road building.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed project wide. Service connections to the new mains are on-going project wide. CenterPoint Energy will coordinate with residents directly on service impacts. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD. Underground line relocation area planned tentatively towards the end of July.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and is scheduled to begin after the holiday weekend and last approximately 2-3 weeks.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
July 11, 2025
Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.
Project Updated Reminder
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
Week of July 14th
General Project Note:
Tree clearing and grubbing is planned to resume in the phase 3 – 5 areas starting Monday. Trees were previously marked for removal and may be refreshed with new paint.
Phase 1: Conestoga Neighborhood & Kiowa Circle
Utility crews plan to finish up watermain work on Kiowa Circle as well as storm sewer in the Conestoga neighborhood.
Phase 2: Del Rio
Residents will begin being placed on temporary water starting Monday. Crews plan to begin utility work on Del Rio Drive between Santa Fe Trail and Iroquois Avenue. Due to Del Rio being a dead end street, residents may have to park outside of the construction area multiple days in a row during working hours while the utility & street work is completed. It is the intent of the project team to have driveway access restored at the end of each day. Please look for notices that will be delivered with more information on times, dates, and locations as the project advances.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Watermain lining is scheduled to start early in the week with crews televising the line ahead of installation of the liner. Sections of the street will be reclaimed ahead of utility work in the street starting Thursday. Please follow all posted no parking signs during working hours.
Phase 4A: Frontier Trail (77th Street to 78th Street)
Crews plan to begin laying out temporary water piping along Frontier Trail between W 77th Street and W 78th Street. This area is also planned to be reclaimed starting Thursday. Please follow all posted no parking signs during working hours.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Final removals and pavement reclamation will begin in a few weeks. This will be followed by concrete curb & gutter and driveway placement then gravel tolerancing in preparation for paving.
Phase 2: Del Rio
Utilities are planned to last approximately 5 weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Lining of the existing watermain and replacement of existing water services are anticipated to last approximately 7 weeks.
Phase 4: Frontier Trail (Highland Drive to 78th Street)
Phase 4A will consist of the area between W 77th Street and W 78th Street. Work here is scheduled to begin in mid July with the remaining portion of Frontier planned to start towards the end of July.
Phase 5: Highland Drive
Work in this area isn’t planned to begin until mid to late August.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed project wide. Service connections to the new mains are on-going project wide. CenterPoint Energy will coordinate with residents directly on service impacts. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD. Underground line relocation area planned tentatively towards the end of July.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and is scheduled to begin after the holiday weekend and last approximately 2-3 weeks.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Resident’s are asked to relocate any plantings near the road way that they wish to save prior to work beginning.
July 3, 2025
Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.
Project Updated Reminder
- Garbage & Recycling: Some haulers have been revising their garbage/recycling truck schedules in order to avoid the construction vehicles during working hours. In order for the contractor to accommodate bringing cans to the trucks in a timely manner, please have all garbages to the ends of driveways by 6:30am. Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. If your garbage has been missed and were out by 6:30am please contact one of the project contacts.
Week of July 7th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Utility crews will continue with watermain, sanitary sewer, and storm sewer work along Frontier Trail (from Conestoga Trail to Kiowa Circle) and Kiowa Circle area in the Phase 1 portion of the project. Temporary mailboxes have been set up and are active. Affected residents have been notified.
Phase 2: Del Rio
Temporary water system has been set up and is undergoing testing. A separate notice will go out to those requiring temporary water in this phase when hook-ups are ready to begin. Temporary mailboxes have been set up and are active. Affected residents have been notified. The temporary bank is in the intersection of Iroquois Avenue and Laredo Drive.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Temporary water piping began being placed during the week of 6/23 and will continue to be placed and begin testing. A separate notice will go out to those requiring temporary water in this phase when hook-ups are ready to begin. Watermain lining pits are scheduled to begin being dug early in the week pending weather.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Final removals and pavement reclamation will begin in a few weeks. This will be followed by concrete curb & gutter and driveway placement then gravel tolerancing in preparation for paving.
Phase 2: Del Rio
Utilities are planned to last approximately 5 weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Lining of the existing watermain and replacement of existing water services are anticipated to last approximately 7 weeks.
Phase 4: Frontier Trail (Highland Drive to 78th Street)
Work in this area isn’t planned to begin until late July. Tree clearing is tentatively scheduled for mid-July.
Phase 5: Highland Drive
Work in this area isn’t planned to begin until mid to late August. Tree clearing is tentatively scheduled for mid-July.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed project wide. Service connections to the new mains are on-going project wide. CenterPoint Energy will coordinate with residents directly on service impacts. If you have no gas please contact CenterPoint Energy at 1-800-245-2377 or 612-372-4757
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD. Underground line relocation area planned tentatively towards the end of July.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and is scheduled to begin after the holiday weekend and last approximately 2-3 weeks.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Residents are asked to relocate any plantings near the roadway that they wish to save prior to work beginning.
June 27, 2025
Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.
Week of June 30th
Phase 1: Conestoga Neighborhood & Kiowa Circle
Utility crews will continue with watermain, sanitary sewer, and storm sewer work along Frontier Trail (from Conestoga Trail to Kiowa Circle) and Kiowa Circle area in the Phase 1 portion of the project. Temporary mailboxes have been set up and are active. Affected resident’s have been notified.
Phase 2: Del Rio
Temporary water hook-ups are planned to begin early in the week. A separate notice will go out to those requiring temporary water in this phase when hook-ups are ready to begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Temporary water piping began being placed during the week of 6/23 and will continue to be placed and begin testing. A separate notice will go out to those requiring temporary water in this phase when hook-ups are ready to begin. Watermain lining pits are scheduled to begin being dug early in the week pending weather. Driveway removals are also scheduled to begin in preparation for work, temporary gravel patches will be placed until work is completed.
Looking Ahead
Phase 1: Conestoga Neighborhood & Kiowa Circle
Final removals and pavement reclamation will begin in a few weeks. This will be followed by concrete curb & gutter and driveway placement then gravel tolerancing in preparation for paving.
Phase 2: Del Rio
Utilities are planned to last approximately 5 weeks before road building activities begin.
Phase 3: Frontier Trail (Highland Drive to Kiowa Circle)
Lining of the existing watermain and replacement of existing water services are anticipated to last approximately 7 weeks.
Phase 4: Frontier Trail (Highland Drive to 78th Street)
Work in this area isn’t planned to begin until late July. Tree clearing is tentatively scheduled for mid-July.
Phase 5: Highland Drive
Work in this area isn’t planned to begin until mid to late August. Tree clearing is tentatively scheduled for mid-July.
Reminder schedules and phasing are subject to change due to weather, site conditions, and other factors.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed in Kiowa Circle, Del Rio Drive, and Conestoga neighborhood. Service connections to the new mains are scheduled to begin June 20th into the following weeks in those areas. CenterPoint Energy will coordinate with resident’s directly on service impacts. Gas main work has begun along Frontier Trail in the Phase 4 & 5 areas.
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD. Underground line relocation area planned tentatively towards the end of July.
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature.
- Mediacom: Relocation work along Frontier Trail will mainly occur at intersection crossings and is scheduled to begin after the holiday weekend and last approximately 2-3 weeks.
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Garbage & Recycling: Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. Please have all garbages to the ends of driveways by 7am. If your garbage has been missed please contact one of the project contacts.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
- Landscaping: Residents are asked to relocate any plantings near the roadway that they wish to save prior to work beginning.
June 20, 2025
Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.
Week of June 23rd
Phase 1: Conestoga Neighborhood & Kiowa Circle
Utility crews will begin watermain, sanitary sewer, and storm sewer work along Frontier Trail (from Conestoga Trail to Kiowa Circle) and Kiowa Circle area in the Phase 1 portion of the project. Some residents will be placed on temporary water while this work is completed and have been notified ahead of time if required.
Phase 2: Del Rio
Reclamation of Del Rio Drive and Iroquois Avenue is scheduled to start on Wednesday, June 25th. Please follow all posted no parking signs. This activity is subject to change based on weather. Driveway removals are also scheduled to begin starting Monday. These impacts will be short in duration as crews remove driveways and place a gravel patch back in to resume access.
Temporary water is also planned to begin being placed. This process will take some time to place and complete all required testing before it can be operational. A separate notice will go out to those requiring temporary water in this phase when hooks are ready to begin.
Looking Ahead
Del Rio will start to see more utility work begin in the coming weeks as utility crews transition to the area.
In the Phase 1 area, to date, only pavement, driveway, and curb removals have occurred in areas where utility work is already underway. In the coming weeks, crews will complete the remaining removals throughout the Phase 1 area in preparation for replacements.
The Contractor has provided an updated master schedule. Please see below for an updated timeline:
Phase 1 (Conestoga Neighborhood & Kiowa Circle): June – Mid July
Phase 2 (Del Rio): Late June – Mid July
Phase 3 (Frontier Trail from Kiowa Circle to Highland Drive): Late June – Early September
Phase 4 (Frontier Trail): Late July – Late October
Phase 5 (Highland): Late August – Late October
These ranges of time are subject to change and are a general overview of each location. A more detailed schedule will be given as crews approach the dates and begin to transition to the various phases.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed in Kiowa Circle, Del Rio Drive, and Conestoga neighborhood. Service connections to the new mains are scheduled to begin June 20th into the following weeks in those areas. CenterPoint Energy will coordinate with resident’s directly on service impacts. Gas main work has begun along Frontier Trail in the Phase 4 & 5 areas.
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD
- Lumen (CenturyLink): Relocation work is scheduled to begin soon. Impacts should be minor in nature
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Garbage & Recycling: Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps. Please have all garbages to the ends of driveways by 7am.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
June 13, 2025
Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.
Week of June 16th
Utility crews will finish valve bolt replacement and watermain improvements in the Conestoga neighborhood before switching over to storm sewer work early in the week.
Temporary water systems have been set up and hooks ups are anticipated to begin soon ahead of watermain work along Frontier Trail between Conestoga Trail and Kiowa Circle as well as Kiowa Circle.
Watermain work is planned to start along Frontier Trail and Kiowa Circle towards the end of the week.
Looking Ahead
Watermain, sanitary sewer, and storm sewer work in the phase 1 portion of Frontier Trail and Kiowa Circle will occur late next week into the week of June 23rd.
To date, only pavement, driveway, and curb removals have occurred in areas where utility work is already underway. In the coming weeks, crews will complete the remaining removals throughout the Phase 1 area in preparation for replacements.
Residents in the Del Rio area may begin to notice increased traffic control and utility markings (such as flags and paint) in their yards as crews prepare to begin work in that area in the near future.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have been completed in Kiowa Circle, Del Rio Drive, and Conestoga neighborhood. Service connections to the new mains are scheduled to begin June 20th into the following weeks in those areas. CenterPoint Energy will coordinate with resident’s directly on service impacts.
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Garbage & Recycling: Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
June 6, 2025
Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.
Week of June 9th
Utility crews will continue with valve bolt replacement and watermain improvements in the Conestoga neighborhood before switching over to storm sewer work. A few watermain shutdowns will be required to complete the watermain work. Additional notices with more information will be handed out to those affected by the shutdown.
Crews will also begin setting up temporary water hookups for properties that require them. If your property is included, you will receive a separate notice with more information.
In addition, curb and driveway removals are scheduled for the latter half of the week along Frontier Trail and Kiowa Circle. This work is in preparation for upcoming utility installations.
Looking Ahead
Utility crew plans to move into the Kiowa Circle and first phase of the Frontier Trail area to start on watermain, sanitary sewer, and storm sewer work starting the week of June 16th.
To date, only pavement, driveway, and curb removals have occurred in areas where utility work is already underway. In the coming weeks, crews will complete the remaining removals throughout the Phase 1 area in preparation for replacements.
Residents in the Del Rio area may begin to notice increased traffic control and utility markings (such as flags and paint) in their yards as crews prepare to begin work in that area in the near future.
Private UtilitiesWhile outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations have started in the phase 1 and 2 areas of the project.
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Garbage & Recycling: Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
Thank you in advance for your cooperation throughout the project.
May 30, 2025
Week of June 2nd
Utility crews will begin watermain valve bolt replacement and improvements in the Conestoga neighborhood starting on Monday followed by storm sewer improvements in the same area. Utility work is anticipated to last approximately a week in the Conestoga neighborhood. There will be temporary closures of intersections during working hours to complete the work so please use caution and plan for more time when navigating. Temporary watermain shut downs can also be expected. A separate notice will be handed out to those being affected by watermain shutdowns with more information as needed.
Crews will also begin setting up temporary water systems in Phase 1. A separate notice will be delivered to affected homes with more details.
Looking Ahead
Utility crew plans to move into the Kiowa Circle and first phase of the Frontier Trail area to start on watermain, sanitary sewer, and storm sewer work starting the week of June 9th.
Residents in the Del Rio area may start to notice more traffic control and utility markings (flags and paint) in yards as crews prepare to start work in the area over the next few weeks.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations begin after Memorial Day.
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Garbage & Recycling: Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
May 23, 2025
Week of May 26th
Tree removals are now scheduled to begin Tuesday, May 27, due to weather delays. Work will start in the Conestoga neighborhood, then move into the northern part of Frontier, heading south. Crews will focus on Phases 1, 2, and 3 for now. Phases 4 and 5 will be addressed later. Trees marked for removal have a pink “X”.
Street reclamation in Phase 1 is planned for Thursday, May 30. Please avoid parking on the street during work hours and follow posted signs.
Crews will also begin setting up temporary water systems in Phase 1. A separate notice will be delivered to affected homes with more details.
Looking Ahead
Utility crews plan to begin storm sewer work and valve bolt replacement on the watermain starting the week of June 2nd. This may require temporary closure of intersections during working hours while the crews complete the work.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations begin after Memorial Day.
- Xcel Energy: Pole and streetlight relocations are planned. A full schedule is TBD. Xcel plans to place a new pole near the Kerber Ravine along Frontier Trail on Thursday, May 29th
Project Reminders
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Garbage & Recycling: Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
Thank you in advance for your cooperation throughout the project.
May 16, 2025
Overview
The Chanhassen City Council has awarded the 2025 Pavement Rehabilitation Project (25-01) to Ryan Contracting, with work officially beginning soon. The project includes a mix of pavement rehabilitation and reconstruction, along with utility improvements. Bolton & Menk will have staff on-site daily to monitor progress and assist residents.
Key Contacts:
- Troy Vulcan, Senior Construction Rep
📞 (507) 848-0935 | ✉️ troy.vulcan@bolton-menk.com - Karth Whiteside, Project Engineer
📞 (612) 246-5029 | ✉️ karth.whiteside@bolton-menk.com - Ryan Johnson, Project Manager
📞 (952) 426-8335 | ✉️ ryan.johnson@bolton-menk.com
What to Expect
- Drive Carefully: Please slow down in construction zones and watch for workers and equipment. Plan for additional time as you navigate the streets.
- Temporary Systems: Some areas will use temporary mailboxes and water lines. Affected residents will receive advance notice.
- Garbage & Recycling: Place bins at the end of your driveway as usual. Crews may move them for pickup and return them. Labeling bins with your address helps.
- Irrigation & Pet Fencing: Mark any sprinkler heads, underground wires, or fencing near the curb to help crews avoid damage.
Overall Schedule
The schedule is shown below. Please note that it is subject to change. Moving forward a weekly update will be provided on the website with the progress of construction. Any substantial changes or impacts may also be posted periodically throughout the construction. Project staff will try to communicate any major impacts directly affecting access to those residents impacted as soon as possible but keep in mind emergencies can and do arise so there may be a short time period of notification.
Week of May 19th
Tree Story, the tree removal subcontractor, is planning to begin tree removals on Thursday May 22nd. They plan to start in the Conestoga neighborhood before moving into the northern area of Frontier working their way south. Project staff began marking tree removals this past week with a pink X. Project staff also began marking out pavement, driveway, and curb removals in the phase 1 area.
Private Utilities
While outages are not expected, accidents can happen. If a utility is disrupted, the contractor will notify the provider. Please be patient during any service restoration.
Upcoming Utility Work:
- CenterPoint Energy (via Michaels): Gas main relocations begin after Memorial Day.
- Xcel Energy: Pole and streetlight relocations are planned; schedule pending.
Looking Ahead
Removal of the pavement, driveways, and curb in the phase 1 area is anticipated to begin after Memorial Day.
Thank you in advance for your cooperation throughout the project.
April 23, 2025
Public Open House - Please join us!
Wednesday, May 7, 2025
4:30 p.m. - 6:30 p.m.
Chanhassen Public Works Building
7901 Park Place
Chanhassen, MN 55317
At this meeting, you will have an opportunity to learn about the project, share your knowledge of the project area, and ask questions related to the project. This will be an informal meeting with no presentation, so please feel free to join us at any time during the meeting.
March 13, 2025
Tree pruning ahead of the upcoming construction season is scheduled to begin March 17, 2025.
Pro Tree will be the contractor for this project.
Pruning specs are as described:
- Raise all trees growing out over the road to 16 feet vertical clearance, branches that will droop down within 16 feet due to leaf weight will be pruned as well
- Trees and branches below 16 feet but within 6 to 8 feet of the curb edge will be trimmed back using reduction pruning or complete branch removal
- Deadwood 2 inches in diameter and larger over the street will be removed
- Pro Tree will handle all debris disposal.
Please keep in mind:
- Our schedule is highly variable and dependent on weather, location, equipment functionality, emergency work, and other unforeseen circumstances that may impact our ability to perform the job safely. We ask for your patience and understanding if we need to reschedule.
- We do not require anyone to be home while we do our work.
- Our production time typically starts at 8 am and ends around 4 pm.
- Please make sure that full access to the job site is provided to our crew on the scheduled date. and move vehicles that prevent us from parking our equipment.
January 7, 2025
Public Open House - Please join us!
Tuesday, January 28, 2025
4:30 p.m. - 6:30 p.m.
Chanhassen Public Works Building
7901 Park Place
Chanhassen, MN 55317
At this meeting, you will have an opportunity to learn about the project, share your knowledge of the project area, and ask questions related to the project. This will be an informal meeting with no presentation, so please feel free to join us at any time during the meeting.
| Project Stage | Dates |
|---|---|
|
Award Consultant Contract |
October 2024 |
| Neighborhood Project Open House | January 28, 2025 |
| Accept Feasibility Report/Call Public Hearing | January 27, 2025 |
| Public Hearing | February 10, 2025 |
| Bid Opening | April 11, 2025 |
|
Neighborhood Open House |
May 7, 2025 |
|
Assessment Hearing/Award Contract |
May 12, 2025 |
|
Start Construction |
May 26, 2025 |
| Substantial Completion | November 2025 |
| Final Completion | Spring 2026 |