Overview
Changes are coming to Stone Creek Park! Every year, the Chanhassen Parks and Recreation Department selects a park playground for renovation. This ensures that the playgrounds are safe and updated.
If you are a resident of the Stone Creek neighborhood, we want your input! Vote for one of the four options for the new playground.
Project Timeline
The neighborhood will be able to vote again on their preferred concept. The options will include the original concept and the new concepts. (See Layout Options Layout Voting at the bottom of the page)
Another open house is scheduled for Tuesday, June 23, 5:30 p.m., at Chanhassen City Hall. If you can't make it to the meeting and would like to vote on the new concept, images will be uploaded and available for viewing from June 18-23.
Timetable
- April - Prepared and distributed RFP to Playground Vendors
- May 26 - Neighborhood Open House; Park & Recreation Commission Meeting
- Neighborhood selects favorite playground design/company
- June 23 - Second Neighborhood Open House; Park & Recreation Commission Meeting
- July 13 - City Council Approves playground equipment contract
- July 15 - Contracts signed & playground equipment ordered
- 8-10 weeks manufacturing production schedule
- September - Playground equipment delivered
- September - Existing playground removed
- October - Installation begins (2-3 week build)
- October (late) - Ribbon Cutting
*Timetable subject to change